11/24/2020
|
Notification of In-Service Date and Construction Completion Date of 11/20/20 electronically filed by Tanner Wolffram on behalf of Ohio Power Company. |
05/01/2020
|
Notification of In-Service Date and Construction Completion Date for the Willow Island- Mill Creek 138 kV Transmission Line Extension Project #3 electronically filed by Tanner Wolffram on behalf of Ohio Power Company. |
01/22/2020
|
Notice of start of construction for the Willow Island-Mill Creek 138 kV Transmission Line Extension Project #3 electronically filed by Tanner Wolffram on behalf of Ohio Power Company. |
10/11/2019
|
Staff Report of Investigation electronically filed by Mr. Matt Butler on behalf of Staff of OPSB. |
09/25/2019
|
Proof of Compliance Letter and associated exhibits for the Willow Island- Mill Creek 138 kV Transmission Line Extension Project #3. electronically filed by Tanner Wolffram on behalf of Ohio Power Company. |
09/19/2019
|
Notice LON for the Willow Island- Mill Creek 138 kV Transmission Line Extension Project #3 electronically filed by Tanner Wolffram on behalf of Ohio Power Company. |
09/12/2019
|
In the matter of the Pre-Application Notification Letter electronically filed by Tanner Wolffram on behalf of Ohio Power Company. |