10/28/2020
|
Notification Construction Completion Date for the Adjustment to Gristmill-Gemini 138 kV Transmission Line Project electronically filed by Tanner Wolffram on behalf of AEP Ohio Transmission Company, Inc. |
10/01/2019
|
Notice of Start of Construction for the Adjustment to Gristmill-Gemini 138 kV Transmission Line Project electronically filed by Tanner Wolffram on behalf of AEP Ohio Transmission Company, Inc. |
09/05/2019
|
Service Notice. |
09/05/2019
|
Staff Report of Investigation electronically filed by Mr. Matt Butler on behalf of Staff of OPSB. |
08/26/2019
|
Proof of Compliance Letter for the Adjustment to Gristmill-Gemini 138 kV Transmission Line Project and the associated exhibits electronically filed by Tanner Wolffram on behalf of AEP Ohio Transmission Company, Inc. |
08/14/2019
|
Letter of Notification for Adjustment to Gristmill-Gemini 138 kV Transmission Line Project electronically filed by Tanner Wolffram on behalf of AEP Ohio Transmission Company, Inc. |
08/07/2019
|
In the matter of the Pre-Application Notification Letter and Request for Expedited Treatment electronically filed by Ms. Christen M. Blend on behalf of AEP Ohio Transmission Company, Inc. |