10/26/2021
|
Notification of Completion of Construction of West Milton Substation Expansion electronically filed by Ms. Sarah Howdeshelt on behalf of The Dayton Power and Light Company. |
07/13/2020
|
Notice of Construction Start Date electronically filed by Mr. Michael F. Russ on behalf of The Dayton Power and Light Company. |
07/13/2020
|
Notice of Compliance with Notification to affected property owners of commencement of construction electronically filed by Mr. Michael F. Russ on behalf of The Dayton Power and Light Company. |
12/03/2019
|
Service Notice |
12/03/2019
|
Staff Report of Investigation electronically filed by Mr. Matt Butler on behalf of Staff of OPSB. |
11/05/2019
|
Response Letter electronically filed by Mrs. Jessica E Kellie on behalf of The Dayton Power and Light Company. |
09/13/2019
|
Public Notice of The Dayton Power and Light Company of Construction Notice for the West Milton Substation Expansion Project electronically filed by Mr. Randall V Griffin on behalf of The Dayton Power and Light Company. |
09/10/2019
|
Notice of Construction of West Milton Substation Expansion before the Ohio Power Siting Board electronically filed by Mr. Randall V Griffin on behalf of The Dayton Power and Light Company. |
08/16/2019
|
In the matter of the Pre-Application Construction Notification of The Dayton Power and Light Company for the West Milton Substation Expansion Project electronically filed by Mr. Randall V Griffin on behalf of The Dayton Power and Light Company. |