11/06/2020 | Notice of completion of Kirk-Jug Street 345 kV Pole Installation Project as of September 12, 2019 electronically filed by Tanner Wolffram on behalf of AEP Ohio Transmission Company, Inc. | 2 |
08/06/2019 | Notification of Start of Construction for the Kirk- Jug Street 346 kV Pole Installation Project electronically filed by Tanner Wolffram on behalf of AEP Ohio Transmission Company, Inc. | 2 |
07/02/2019 | Service Notice | 2 |
07/01/2019 | Staff Report of Investigation electronically filed by Mr. Matt Butler on behalf of Staff of OPSB. | 4 |
06/14/2019 | Construction Notice for Kirk- Jug Street 345 kV Pole Installation Project electronically filed by Mrs. Jaclyn Knies on behalf of AEP Ohio Transmission Company, Inc. | 55 |
06/13/2019 | Supplemental pre-application notification letter for the above-referenced project electronically filed by Ms. Christen M. Blend on behalf of AEP Ohio Transmission Company, Inc. | 3 |
06/06/2019 | In the Matter of the Pre-Application Notification Letter electronically filed by Ms. Christen M. Blend on behalf of AEP Ohio Transmission Company, Inc. | 3 |