01/29/2021
|
Notification of In-Service Date for the Hyatt 345kV Station Expansion Project as of December 11, 2020 electronically filed by Tanner Wolffram on behalf of Ohio Power Company. |
12/18/2019
|
Construction Notification Start for the Hyatt 345 kV Station Expansion Project electronically filed by Tanner Wolffram on behalf of Ohio Power Company. |
08/12/2019
|
Staff Report of Investigation electronically filed by Mr. Matt Butler on behalf of Staff of OPSB. |
08/12/2019
|
Service Notice |
05/20/2019
|
Construction Notice for Hyatt 345 kV Station Expansion Project electronically filed by Ms. Christen M. Blend on behalf of AEP Ohio Transmission Company, Inc. |
04/22/2019
|
In the Matter of the Pre-Application Notification Letter electronically filed by Ms. Christen M. Blend on behalf of AEP Ohio Transmission Power Company, Inc. |