11/06/2020
|
Notice of completion of Devola-Mill Creek 138 kV Transmission Line Project as of October 23, 2020lectronically filed by Tanner Wolffram on behalf of AEP Ohio Transmission Company, Inc. |
02/18/2020
|
Notice of Adjustments for the Devola-Mill Creek 138 kV Transmission Line Project electronically filed by Tanner Wolffram on behalf of AEP Ohio Transmission Company, Inc. |
03/14/2019
|
Notice (Acceptance of Staff Conditions) electronically filed by Ms. Christen M. Blend on behalf of AEP Ohio Transmission Power Company, Inc. |
03/13/2019
|
Service Notice |
03/12/2019
|
Staff Report of Investigation electronically filed by Mr. Matt Butler on behalf of Staff of OPSB. |
12/18/2018
|
Letter of Notification for the Devola-Mill Creek 138kV Transmission Line Project electronically filed by Ms. Christen M. Blend on behalf of AEP Ohio Transmission Power Company, Inc. |
12/14/2018
|
In the matter of the Pre-Application Notification Letter electronically filed by Ms. Christen M. Blend on behalf of AEP Ohio Transmission Power Company, Inc. |