CASE NUMBER: 18-1572-EL-BNR
CASE DESCRIPTION: Duke Energy Ohio, Inc. Ebenezer Substation Project
DOCUMENT SIGNED ON: 4/26/2024
DATE OF SERVICE: ________________________________________
01/02/2019 Letter of Completion for the Duke Energy Ohio Case No. 18-1572-EL-BNR F1783 – 138kV Ebenezer Substation Expansion electronically filed by Carys Cochern on behalf of Duke Energy.
11/14/2018 Correspondence Adopting and accepting the required condition electronically filed by Carys Cochern on behalf of Kingery, Jeanne W Ms.
11/13/2018 Service Notice
11/13/2018 Staff Report of Investigation electronically filed by Mr. Matt Butler on behalf of Staff of OPSB.
11/05/2018 Notice of Compliance electronically filed by Carys Cochern on behalf of Ms. Jeanne W. Kingery.
10/29/2018 Application electronically filed by Ms. Emily Olive on behalf of Duke Energy Ohio and D'Ascenzo, Rocco O. Mr. and Kingery, Jeanne W. Ms.
10/24/2018 In the matter of the Construction Notice for the F1783 – 138 kV Ebenezer Substation Expansion planned to begin November 26, 2018 electronically filed by Carys Cochern on behalf of Kingery, Jeanne W Ms.