CASE NUMBER: 18-1396-EL-BNR
CASE DESCRIPTION: Brookside-Leaside 138kV T-Line Switch Structure Addition Project
DOCUMENT SIGNED ON: 5/10/2024
DATE OF SERVICE: ________________________________________
04/04/2019 Notice stating that construction of Brookside-Leaside 138 kV Transmission Line Switch Structure Addition Project was completed on March 31. 2019 filed by Bryksenkova on behalf of FirstEnergy Service Company.
02/28/2019 Construction Notice filed by N. Bryksenkova on behalf of FirstEnergy Service Company.
02/13/2019 Service Notice (Staff Report)
02/13/2019 Staff Report of Investigation electronically filed by Mr. Matt Butler on behalf of Staff of OPSB.
01/22/2019 Construction notice application filed by N. Bryksenkova on behalf of FirstEnergy Service Company.
12/24/2018 In the matter of the Pre-Application Notification Letter filed by N. Bryksenkova on behalf of FirstEnergy Service Company.