DIS - Case Record for 18-1335-EL-BTX Skip to main content

Case Record For:

18-1335-EL-BTX

File a Public Comment
Case Title: Wood County 138-kV Reinforcement Project
Status: OPEN-OPEN
Industry Code: EL-ELECTRIC
Purpose Code: BTX-Application for a Certificate/ Gas or Electric
Date Opened: 8/29/2018
Date Closed:
Printable Docket Card Service List
View per page
Date FiledSummaryPages
09/26/2023Application to Amend the Certificate of Environmental Compatibility and Public Need Issued for the Wood County 138kV Reinforcement Project (Part V of V) electronically filed by Mr. Lawrence B. Hughes on behalf of American Transmission Systems, Inc.9
09/26/2023Application to Amend the Certificate of Environmental Compatibility and Public Need Issued for the Wood County 138kV Reinforcement Project (Part IV of V) electronically filed by Mr. Lawrence B. Hughes on behalf of American Transmission Systems, Inc.15
09/26/2023Application to Amend the Certificate of Environmental Compatibility and Public Need Issued for the Wood County 138 kV Reinforcement Project (Part III of V) electronically filed by Mr. Lawrence B. Hughes on behalf of American Transmission Systems, Inc.28
09/26/2023Application to Amend the Certificate of Environmental Compatibility and Public Need issued for the Wood County 138kV Reinforcement Project (Part II of V) electronically filed by Mr. Lawrence B. Hughes on behalf of American Transmission Systems, Inc.6
09/26/2023In the Matter of the Application to Amend the Certificate of Environmental Compatibility and Public Need issued for the Wood County 138kV Reinforcement Project (Part I of V) electronically filed by Mr. Lawrence B. Hughes on behalf of American Transmission Systems, Inc.75
09/12/2023Correspondence regarding the No Hazard Letters of FAA Determination for Structures 3 & 4 per Condition 16. electronically filed by Mr. Lawrence B. Hughes on behalf of American Transmission Systems, Inc.20
09/11/2023Notice of Substitution of Counsel electronically filed by Ms. Devan K. Flahive on behalf of American Transmission Systems Incorporated.4
08/16/2023Response to Pre-Construction Meeting Data Requests From Staff electronically filed by Ms. Devan K. Flahive on behalf of American Transmission Systems Incorporated.3
07/28/2023Notice of Preconstruction Conference #2 Agenda and of Compliance with Certificate Conditions 2, 3, and 9 electronically filed by Ms. Devan K. Flahive on behalf of AmericanTransmission Systems Incorporated.48
03/16/2022Notice: Start of Construction electronically filed by Ms. Devan K. Flahive on behalf of American Transmission Systems Incorporated.2
03/16/2022Preconstruction Conference #1 Agenda electronically filed by Ms. Devan K. Flahive on behalf of American Transmission Systems Incorporated.3
02/10/2022Notice of Compliance with Conditions 3, 8, 9, and 16 electronically filed by Ms. Devan K. Flahive on behalf of American Transmission Systems Incorporated.51
01/07/2021Notice of Substitution of Counsel electronically filed by Mr. Robert J Schmidt on behalf of American Transmission Systems Inc.3
01/16/2020Service Notice3
01/16/2020Opinion & Order that the Ohio Power Siting Board approves and adopts the stipulation between American Transmission Systems, Incorporated and the Ohio Power Siting Board Staff; adopts a separate joint stipulation between American Transmission Systems, Incorporated and American Municipal Power, Inc.; and directs that a certificate be issued to American Transmission Systems, Incorporated for construction of a 138-kilovolt transmission line project electronically filed by Docketing.35
11/26/2019Transcript in the Matter of the Application of American Transmission Systems, Inc. for a Certificate of Environmental Compatibility and Public Need for the Construction of the Wood County 138 KV Reinforcement Project, hearing held on November 7th, 2019. electronically filed by Mr. Ken Spencer on behalf of Armstrong & Okey, Inc. and Spencer, Michael O. Mr.33
11/15/2019Transcript for hearing held on 10/24/19 at the Ohio Department of Transportation, 317 East Poe Road, Bowling Green, Ohio filed by Huntley Reporting Service, Inc.37
11/04/2019Joint Stipulation between ATSI and Staff of the Ohio Power Siting Board electronically filed by Mr. Robert J Schmidt on behalf of American Transmission Systems Inc.18
11/04/2019Notice of the Filing of Response Letters Concerning Ohio Historic Preservation Office Consultations Related to Project electronically filed by Mr. Robert J Schmidt on behalf of American Transmission Systems Inc.5
11/04/2019Notice of Filing of Response Letters Concerning Ohio Historic Preservation Office Consultations for Project electronically filed by Mr. Robert J Schmidt on behalf of American Transmission Systems Inc.5
10/29/2019Testimony of Scott Humphrys on Behalf of Applicant, American Transmission Systems, Incorporated electronically filed by Mr. Robert J Schmidt on behalf of American Transmission Systems Inc.23
10/18/2019Notice Of Applicant's Filing of Statement of Issues for Cross-Examination at Adjudicatory Hearing electronically filed by Mr. Robert J Schmidt on behalf of American Transmission Systems Inc.4
10/16/2019Joint Stipulation between American Municipal Power, Inc. and American Transmission Systems, Incorporated electronically filed by Mr. Robert J Schmidt on behalf of American Transmission Systems Inc.7
10/15/2019Proof of Pub of Second Public Notice and Notice of Mailing of Public Official, Library and Property Owner Notification Letters. electronically filed by Mr. Robert J Schmidt on behalf of American Transmission Systems Inc.90
10/09/2019Service Notice.4
10/09/2019Staff Report of Investigation electronically filed by Mr. Matt Butler on behalf of Staff of OPSB.49
09/04/2019Administrative Law Judge Entry granting motion to intervene, granting motion to reissue procedural schedule, rescheduling hearings, ordering ATSI to notice the application and rescheduled hearings, setting deadline to file staff report, and setting deadlines to file issues lists and testimony electronically filed by Heather A Chilcote on behalf of Patricia A. Schabo, Administrative Law Judge, Power Siting Board6
09/04/2019Service Notice2
08/15/2019Motion to Reissue Procedural Order and Memorandum in Support electronically filed by Mr. Robert J Schmidt on behalf of American Transmission Systems Inc.6
06/17/2019Affidavit and copy of the public notice notifying the public of the cancellation of the public hearing previously scheduled in this matter filed by S. Humphrys on behalf of FirstEnergy Service Company.41
05/23/2019Service Notice2
05/23/2019Administrative Law Judge Entry granting Movants' motion to suspend procedural schedule electronically filed by Heather A Chilcote on behalf of Patricia A. Schabo, Administrative Law Judge, Power Siting Board.5
05/23/2019Joint Motion to Suspend Procedural Order and Memorandum in Support electronically filed by Mr. Robert J. Schmidt on behalf of American Transmission Systems Inc.7
05/22/2019Motion to Intervene and Memorandum in Support of American Municipal Power, Inc. electronically filed by Barbara E Johnson on behalf of American Municipal Power, Inc.7
05/09/2019Notice of the Filing of Supplemental Information for Project electronically filed by Mr. Robert J. Schmidt on behalf of American Transmission Systems Inc.2
04/29/2019Application of the Wood County 138-kV Reinforcement Project filed by S. Humphrys on behalf of FirstEnergy Service Company.119
04/12/2019Service Notice2
04/11/2019Administrative Law Judge Entry setting procedural schedule electronically filed by Heather A Chilcote on behalf of Patricia A. Schabo, Administrative Law Judge, Power Siting Board.6
04/02/2019Proof of Payment of Application Fee electronically filed by Mr. Robert J Schmidt on behalf of American Transmission Systems Inc.3
03/01/2019Affidavit of Proof of Service filed by S. Humphrys on behalf of FirstEnergy Service Company.3
02/19/2019Notice of Compliance filed by T. Turkenton on behalf of PUCO Staff.4
01/22/2019Notice of additional information, consequently, no changes to the project filed by S. Humphrys on behalf of FirstEnergy Service Company.4
12/19/2018Application for a Certificate of Environmental Compatibility and Public Need (Part 8 of 8) electronically filed by Mr. Robert J Schmidt on behalf of American Transmission Systems Inc.21
12/19/2018Application for a Certificate of Environmental Compatibility and Public Need (Part 7 of 8) electronically filed by Mr. Robert J Schmidt on behalf of American Transmission Systems Inc.21
12/19/2018Application for a Certificate of Environmental Compatibility and Public Need (Part 6 of 8) electronically filed by Mr. Robert J Schmidt on behalf of American Transmission Systems Inc.7
12/19/2018Application for a Certificate of Environmental Compatibility and Public Need (Part 5 of 8) electronically filed by Mr. Robert J Schmidt on behalf of American Transmission Systems Inc.22
12/19/2018Application for a Certificate of Environmental Compatibility and Public Need (Part 4 of 8) electronically filed by Mr. Robert J Schmidt on behalf of American Transmission Systems Inc.6
12/19/2018Application for a Certificate of Environmental Compatibility and Public Need (Part 3 of 8) electronically filed by Mr. Robert J Schmidt on behalf of American Transmission Systems Inc.6
12/19/2018Application for a Certificate of Environmental Compatibility and Public Need (Part 2 of 8) electronically filed by Mr. Robert J Schmidt on behalf of American Transmission Systems Inc.71
12/19/2018Application for a Certificate of Environmental Compatibility and Public Need (Part 1 of 8) electronically filed by Mr. Robert J Schmidt on behalf of American Transmission Systems Inc..93
12/19/2018Application for Certificate of Environmental Compatibility and Public Need -- Docketing Letter and Affidavit electronically filed by Mr. Robert J Schmidt on behalf of American Transmission Systems Inc.5
09/28/2018Affidavit of Proof of Service filed by Scott M. Humphrys on behalf of FirstEnergy Service Company. 15
08/29/2018In the matter of the pre-application notification letter of American Transmission Systems, Inc. for Wood County 138-kV Reinforcement Project.1