DIS - Case Record for 18-1333-EL-BNR Skip to main content

Case Record For:

18-1333-EL-BNR

File a Public Comment
Case Title: Southwest Lima 345kV Transmission Line Extension Project
Status: OPEN-OPEN
Industry Code: EL-ELECTRIC
Purpose Code: BNR-Construction notification report
Date Opened: 8/27/2018
Date Closed:
Printable Docket Card Service List
View per page
Date FiledSummaryPages
01/15/2019Notice of Construction Start Date, Completion Date and In-Service Date electronically filed by Mr. Hector Garcia on behalf of AEP Ohio Transmission Company.2
11/20/2018Notice of Acceptance of Staff Condition electronically filed by Ms. Christen M. Blend on behalf of AEP Ohio Transmission Power Company, Inc.2
11/20/2018Service Notice2
11/20/2018Staff Report of Investigation electronically filed by Mr. Matt Butler on behalf of Staff of OPSB.5
09/24/2018Notice (Proof of Compliance with O.A.C. 4906-6-07) electronically filed by Ms. Christen M. Blend on behalf of AEP Ohio Transmission Power Company, Inc.11
08/31/2018Application (Construction Notice) electronically filed by Ms. Christen M. Blend on behalf of AEP Ohio Transmission Power Company, Inc.79
08/27/2018In the matter of the (Pre-Application Notification Letter) electronically filed by Ms. Christen M. Blend on behalf of AEP Ohio Transmission Power Company, Inc.2