Date Filed | Summary | Pages |
12/13/2019 | Construction Notice Seville-Star 138 kV Transmission Line Structure Replacement Project filed by Scott M. Humphrys, Transmission Siting Supervisor on behalf of FirstEnergy Service Company. | 1 |
11/16/2018 | Construction Notice Seville-Star 138 kV Transmission Line Structure Replacement Project that construction on this Project, which was approved on October 1, 2017, is expected to begin on November 23, 2018. We will notify you once the project has been completed. | 1 |
09/24/2018 | Service Notice | 2 |
09/24/2018 | Staff Report of Investigation electronically filed by Mr. Matt Butler on behalf of Staff of OPSB. | 4 |
07/02/2018 | Construction Notice application for the Seville-Star 138kV Transmission Line Structure Replacement Project filed by S. Humphrys on behalf of ATSI. | 36 |
06/22/2018 | In the matter of the Pre-Application Notice Letter electronically filed by Mr. Robert J Schmidt on behalf of American Transmission Systems Inc. | 2 |