12/19/2018
|
Notice that construction on the Dobbins-Toronto 138 kV Transmission Line Structure Replacement project was completed on November 16, 2018 filed by W. Beutler on behalf of FirstEnergy Service Company. |
09/27/2018
|
Construction Notice - Dobbins-Toronto 138 kV Transmission Line Structure Replacement Project filed by W. Beutler on behalf of FirstEnergy Service Company. |
09/14/2018
|
Notice of additional properties to be included in the application and one additional owner filed by W. Beutler on behalf of FirstEnergy Service Company. |
09/07/2018
|
Service Notice |
09/07/2018
|
Staff Report of Investigation electronically filed by Mr. Matt Butler on behalf of Staff of OPSB. |
06/22/2018
|
Construction Notice Dobbins-Toronto 138 kV Transmission Line
Structure Replacement Project filed by William R. Beutler, P.E. on behalf of FirstEnergy Service Company. |
05/29/2018
|
In the matter of the Pre-Application Notification Letter for the Dobbins-Toronto 138 kV Transmission Line Structure Replacement Project William R. Beutler, P. E. on behalf of FirstEnergy Service Company. |