11/06/2020
|
Notice of completion of the Adjustment to Heppner-Rhodes 138 kV Transmission Line Rebuild Project as of December 27, 2019 electronically filed by Tanner Wolffram on behalf of AEP Ohio Transmission Company, Inc. |
08/21/2019
|
Notice of Construction Start Date electronically filed by Tanner Wolffram on behalf of AEP Ohio Transmission Company, Inc. |
06/25/2018
|
Acceptance of Staff Condition electronically filed by Ms. Christen M. Blend on behalf of AEP Ohio Transmission Power Company, Inc. |
06/22/2018
|
Service Notice (OPSB) |
06/22/2018
|
Staff Report of Investigation electronically filed by Adam Bargar on behalf of Staff of OPSB. |
06/19/2018
|
Notification - Supplemental to Proof of Compliance filed 6/6/2018 electronically filed by Ms. Christen M. Blend on behalf of AEP Ohio Transmission Power Company, Inc. |
06/06/2018
|
Notification (Proof of Compliance with O.A.C. 4906-6-07 and 4906-6-08) electronically filed by Ms. Christen M. Blend on behalf of AEP Ohio Transmission Power Company, Inc. |
05/31/2018
|
Letter of Notification electronically filed by Ms. Christen M. Blend on behalf of AEP Ohio Transmission Power Company, Inc. |
05/24/2018
|
In the matter of the Pre-Application Notification Letter electronically filed by Ms. Christen M. Blend on behalf of AEP Ohio Transmission Power Company, Inc. |