DIS - Case Record for 18-0423-EL-ACP Skip to main content
      
      
CASE NUMBER: 18-0423-EL-ACP
CASE DESCRIPTION: South Bay Energy Corp.
DOCUMENT SIGNED ON: 4/24/2024
DATE OF SERVICE: ________________________________________
09/26/2019 Finding & Order that the Commission finds South Bay Energy Corp. has not satisfied its 2017 renewable portfolio standard (RPS) compliance obligations and that, therefore, an alternative compliance payment is warranted. The Commission directs South Bay Energy Corp. to remit to the Commission a payment, required under R.C. 4928.64, in the amount of $350.48. electronically filed by Docketing Staff.
09/26/2019 Service Notice
02/20/2019 Staff Review and Recommendation electronically filed by Mr. Stuart M. Siegfried on behalf of PUCO Staff.
03/27/2018 In the matter of the RPS Compliance Filing Report for the 2017 Compliance Year electronically filed by Mr. Alex Baldassano on behalf of South Bay Energy Corp.