Date Filed | Summary | Pages |
12/10/2018 | Letter of Notification and Construction Notice stating that the projects were completed on November 30, 2018 filed by N. Bryksenkova. on behalf of FirstEnergy Service Company. | 1 |
02/26/2018 | Notice that project will commence on March 1, 2018, if the automatic approval date is not suspended- filed by N. Bryksenkova on behalf of FirstEnergy Service Company. | 1 |
02/20/2018 | Service Notice | 2 |
02/20/2018 | Staff Report of Investigation electronically filed by Mr. Matt Butler on behalf of Staff of OPSB. | 4 |
02/05/2018 | Construction Notice Clark-Urbana 138 kV Loop Eastern Connection Centerline Adjustment to Broadview Substation Project filed by Nataliya Bryksenkova on behalf of FirstEnergy Service Company. | 76 |
01/17/2018 | In the matter of the Filing of the Pre-Application Letter for Project electronically filed by Mr. Robert J Schmidt on behalf of American Transmission Systems Inc. | 2 |