10/05/2018
|
Notice of completion of project filed by W. Beutler on behalf of FirstEnergy Service Company. |
05/10/2018
|
Supplemental information regarding construction filed by W. Buetler on behalf of FirstEnergy Service Company. |
03/13/2018
|
Letter of Notification for the East Springfield-London #2 138 kV Transmission Line Extensions to North Titus Substation Project stating that the construction will commence on March 12, 2018 filed by W. Beutler on behalf of FirstEnergy Service Company.
|
02/26/2018
|
Service Notice |
02/26/2018
|
Staff Report of Investigation electronically filed by Mr. Matt Butler on behalf of Staff of OPSB |
02/20/2018
|
Notification of the Submittal of Supplemental Information for Application electronically filed by Mr. Robert J Schmidt on behalf of American Transmission Systems Inc. |
02/09/2018
|
Proof of Pub of Notice of Project electronically filed by Mr. Robert J Schmidt on behalf of American Transmission Systems Inc. |
02/02/2018
|
Letter of Notification filed by W. Beutler on behalf of FirstEnergy Service Company. |
02/02/2018
|
Letter of Notification (Part 4 of 4) electronically filed by Mr. Robert J. Schmidt on behalf of American Transmission Systems Inc. |
02/02/2018
|
Letter of Notification (Part 3 of 4) electronically filed by Mr. Robert J. Schmidt on behalf of American Transmission Systems Inc. |
02/02/2018
|
Letter of Notification (Part 2 of 4) electronically filed by Mr. Robert J. Schmidt on behalf of American Transmission Systems Inc. |
02/02/2018
|
Letter of Notification (Part 1 of 4) electronically filed by Mr. Robert J. Schmidt on behalf of American Transmission Systems Inc. |
01/12/2018
|
In the matter of the pre-application notification letter for East Springfield-London #2 138kV Transmission Line Extension to North Titus Substation Project electronically filed by Mr. Robert J Schmidt on behalf of American Transmission Systems Inc. |