Date Filed | Summary | Pages |
09/06/2024 | Notice of Proof of Compliance with the Condition 14 and 21 electronically filed by Hector Garcia-Santana on behalf of AEP Ohio Transmission Company, Inc. | 116 |
08/22/2024 | Notice of Proof of Compliance with Notice to Homeowners/Tenants of Construction Start Date electronically filed by Hector Garcia-Santana on behalf of Ohio Power Company. | 35 |
08/13/2024 | Notification of Start of Construction for the Pine Ridge Switch-Heppner 138 kV Transmission Line Project electronically filed by Hector Garcia-Santana on behalf of AEP Ohio Transmission Company. | 2 |
07/16/2024 | Proof of Compliance with Condition (7)) electronically filed by Hector Garcia-Santana on behalf of AEP Ohio Transmission Company, Inc. | 53 |
04/03/2024 | Proof of Compliance with Condition (3) electronically filed by Hector Garcia-Santana on behalf of AEP Ohio Transmission Company, Inc. | 10 |
04/03/2024 | Proof of Compliance with Condition (2) electronically filed by Hector Garcia-Santana on behalf of AEP Ohio Transmission Company, Inc. | 6 |
08/23/2023 | Notice of Proof of Compliance with Condition 1 - Second Amendment to the Pine Ridge Heppner 138 kV Transmission Line Project electronically filed by Hector Garcia-Santana on behalf of AEP Ohio Transmission Company, Inc. | 116 |
02/19/2021 | Notice of Pine Ridge Switch – Heppner 138kV Transmission Line Project electronically filed by Tanner Wolffram on behalf of AEP Ohio Transmission Company, Inc. | 157 |
02/21/2019 | Service Notice | 2 |
02/21/2019 | Opinion, Order, and Certificate stating that the Stipulation be approved and adopted and that a certificate be issued to AEP Ohio Transco for the construction, operation, and maintenance of the transmission facility along the preferred route. | 35 |
11/14/2018 | Transcript In the Matter of the Application of AEP Ohio Transmission Company, Incorporated, for a Certificate of Environmental Compatibility and Public Need for the Pine Ridge Switch - Heppner 138kV Transmission Line Project, hearing held before Mr. L. Douglas Jennings Administrative Law Judge, at the Public Utilities Commission of Ohio,
180 East Broad Street, Room 11-C, Columbus, Ohio, called at 10:00 a.m. on Wednesday, October 24th, 2018 electronically filed by Mr. Ken Spencer on behalf of Armstrong & Okey, Inc. and Anderson, Rosemary Foster Mrs. | 15 |
10/29/2018 | Transcript for hearing held on October 10th, 2018 at Northville Elementary School Gymnasium, 11507 Chillicothe Pike, Jackson, Ohio electronically filed by Mr. Ken Spencer on behalf of Armstrong & Okey, Inc. and Grubaugh, Valerie. | 8 |
10/15/2018 | Prefiled Testimony of Jon C. Pawley electronically filed by Ms. Tonnetta Scott on behalf of PUCO. | 6 |
10/15/2018 | Direct Testimony of Alicia M. Cross in Support of the Stipulation and Recommendation electronically filed by Ms. Christen M. Blend on behalf of AEP Ohio Transmission Power Company, Inc. | 29 |
10/15/2018 | Stipulation and Recommendation electronically filed by Ms. Christen M. Blend on behalf of AEP Ohio Transmission Power Company, Inc. | 21 |
10/02/2018 | Notice AEP Ohio Transmission Company, Inc.'s List of Issues electronically filed by Ms. Christen M. Blend on behalf of AEP Ohio Transmission Power Company, Inc. | 3 |
09/25/2018 | Service Notice | 4 |
09/25/2018 | Staff Report of Investigation electronically filed by Mr. Matt Butler on behalf of Staff of OPSB. | 43 |
09/25/2018 | Notice (Proof of Publication of Second Notice) electronically filed by Ms. Christen M. Blend on behalf of AEP Ohio Transmission Power Company, Inc. | 8 |
08/16/2018 | Notification of Initial Proof of Notification Pursuant to O.A.C. 4906-3-09(A)(1) electronically filed by Ms. Christen M. Blend on behalf of AEP Ohio Transmission Power Company, Inc. | 11 |
07/25/2018 | Service Notice | 1 |
07/25/2018 | Administrative Law Judge Entry setting procedural schedule and scheduling local public hearing and evidentiary hearing - electronically filed by Sandra Coffey on behalf of L. Douglas Jennings, Attorney Examiner, Public Utilities Commission of Ohio. | 6 |
06/29/2018 | Notice of Compliance with 4906-3-07 Ohio Administrative Code electronically filed by Ms. Christen M. Blend on behalf of AEP Ohio Transmission Power Company, Inc. | 51 |
05/29/2018 | Letter to inform you that the above referenced application, filed with the Ohio Power Siting Board (Board) on March 29, 2018, has been found to comply with Chapters 4906-01, et seq., of the Ohio Administrative Code (OAC). Filed by PUCO Staff. | 4 |
03/29/2018 | Application (Part 5 of 5) electronically filed by Ms. Christen M. Blend on behalf of AEP Ohio Transmission Power Company, Inc. | 52 |
03/29/2018 | Application (Part 4 of 5) electronically filed by Ms. Christen M. Blend on behalf of AEP Ohio Transmission Power Company, Inc. | 87 |
03/29/2018 | Application (Part 3 of 5) electronically filed by Ms. Christen M. Blend on behalf of AEP Ohio Transmission Power Company, Inc. | 28 |
03/29/2018 | Application (Part 2 of 5) electronically filed by Ms. Christen M. Blend on behalf of AEP Ohio Transmission Power Company, Inc. | 80 |
03/29/2018 | In the matter of the application of AEP Ohio Transmission Company, Inc. for a Certificate of Environmental Compatibility and Public Need for the Pine Ridge Switch-Heppner 138 kV Transmission Line Project electronically filed by Ms. Christen M. Blend on behalf of AEP Ohio Transmission Power Company, Inc. (PART 1 of 5) | 214 |
01/11/2018 | Proof of Pub, Franklin County, electronically filed by Ms. Christen M. Blend on behalf of AEP Ohio Transmission Power Company, Inc. | 4 |
01/09/2018 | Proof of Notification - Letters to Property Owners and Tenants regarding Public Info. Open House electronically filed by Ms. Christen M. Blend on behalf of AEP Ohio Transmission Power Company, Inc. | 4 |
01/04/2018 | In the Matter of the Pre-Application Notification Letter electronically filed by Ms. Christen M. Blend on behalf of AEP Ohio Transmission Power Company, Inc. | 3 |