Date Filed | Summary | Pages |
08/27/2019 | Notice of Commencement and Completion of Construction electronically filed by Tanner Wolffram on behalf of AEP Ohio Transmission Company, Inc. | 2 |
01/11/2018 | Letter of Acceptance of Staff Conditions electronically filed by Ms. Christen M. Blend on behalf of AEP Ohio Transmission Power Company, Inc. | 2 |
01/10/2018 | Service Notice | 2 |
01/10/2018 | Staff Report of Investigation electronically filed by Mr. Matt Butler on behalf of Staff of OPSB. | 6 |
11/13/2017 | Notification (Public Notification Compliance Letter) electronically filed by Ms. Christen M. Blend on behalf of AEP Ohio Transmission Power Company, Inc. | 6 |
11/08/2017 | Proof of Pub electronically filed by Ms. Christen M. Blend on behalf of AEP Ohio Transmission Power Company, Inc. | 4 |
10/18/2017 | Notification - Letter of Notification application for the Trimble 138 kV Transmission Line Extension Project electronically filed by Ms. Christen M. Blend on behalf of AEP Ohio Transmission Power Company, Inc. | 89 |
10/13/2017 | In the matter of the Pre-Application Notification Letter of AEP Ohio Transmission Company, Inc. for a Certificate of Environmental Compatibility and Public Need for the Trimble 138kV Transmission Line Extension electronically filed by Ms. Christen M. Blend on behalf of AEP Ohio Transmission Power Company, Inc. | 3 |