Date Filed | Summary | Pages |
03/15/2018 | Certificate No. 18-WND-IL-GATS-0138 issued. | 3 |
03/14/2018 | Service Notice | 2 |
03/14/2018 | Finding and Order Approving Grand Ridge's application; that the Commission's Docketing Division issue Grand Ridge a certificate as an eligible Ohio renewable energy resource generating facility. | 6 |
01/23/2018 | Staff Review and Recommendation electronically filed by Mark C Bellamy on behalf of PUCO Staff. | 4 |
01/04/2018 | Service Notice | 1 |
01/04/2018 | Attorney Examiner Entry suspending the automatic approval process for this application for certification as an eligible Ohio renewable energy resource generating facility; electronically filed by Vesta R Miller on behalf of Anna Sanyal, Attorney Examiner, Public Utilities Commission of Ohio. | 3 |
12/15/2017 | A reply to redact the capacity of the Grand Ridge Wind Farm based on turbine upgrades electronically filed by Mr. Patrick York on behalf of Grand Ridge Energy LLC. | 2 |
12/13/2017 | Reply to inquiry from the Ohio PUC regarding questions for Application submitted for Certification as an Ohio Renewable Resource Generating Facility electronically filed by Mr. Patrick York on behalf of Grand Ridge Energy LLC. | 2 |
11/16/2017 | In the matter of the application for Certification as an Eligible Ohio Renewable Energy Resource Generating Facility. electronically filed by Mr. Patrick York on behalf of Grand Ridge Energy LLC and Mr. Patrick York. | 14 |