07/11/2018
|
Notice of In-Service Date of 6/12/2018 electronically filed by Ms. Christen M. Blend on behalf of AEP Ohio Transmission Power Company, Inc. |
05/09/2018
|
Notification stating that construction commenced on April 30, 2018 electronically filed by Ms. Christen M. Blend on behalf of AEP Ohio Transmission Power Company, Inc. |
01/11/2018
|
Letter regarding the (Acceptance of Staff’s Conditions) electronically filed by Ms. Christen M. Blend on behalf of AEP Ohio Transmission Power Company, Inc. |
01/10/2018
|
Staff Report of Investigation electronically filed by Mr. Matt Butler on behalf of Staff of OPSB. |
01/10/2018
|
Service Notice |
10/24/2017
|
Notice of compliance electronically filed by Ms. Christen M. Blend on behalf of AEP Ohio Transmission Power Company, Inc. |
10/18/2017
|
Construction Notice electronically filed by Ms. Christen M. Blend on behalf of AEP Ohio Transmission Power Company, Inc. |
10/13/2017
|
In the matter of the Pre-Application Notification Letter of AEP Ohio Transmission Company, Inc. for a Certificate of Environmental Compatibility and Public Need for the Buckley Road-Fostoria Central 138kV Transmission Line Extension Project electronically filed by Ms. Christen M. Blend on behalf of AEP Ohio Transmission Power Company, Inc. |