CASE NUMBER: 17-1566-EL-BLN
CASE DESCRIPTION: Dowling-Midway 138 kV Transmission Line Reconductor Project
DOCUMENT SIGNED ON: 4/28/2024
DATE OF SERVICE: ________________________________________
03/13/2018 Letter of Notification for the Dowling-Midway 138 kV Transmission Line Reconductor Project stating that the Project was placed in service on December 29, 2017 filed by S. Humphrys on behalf of FirstEnergy Service Company.
09/05/2017 Letter of Notification Dowling-Midway 138 kV Transmission Line Reconductor Project filed by Scott M. Humphrys on behalf of FirstEnergy Service Company.
08/15/2017 Service Notice
08/15/2017 Staff Report of Investigation electronically filed by Mr. Matt Butler on behalf of Staff of OPSB.
08/14/2017 Proof of publication filed on behalf of FirstEnergy Service Company by S. Humphrys. (Henry County, Lucas County, Wood County)
07/21/2017 Application (Part 9) Exhibit 6-4 for the Dowling-Midway 138kV Transmission Line Reconductor Project filed by FirstEnergy, S. Humphrys electronically filed by Docketing Staff.
07/21/2017 Application (Part 9) Exhibit 6-3 for the Dowling-Midway 138kV Transmission Line Reconductor Project filed by FirstEnergy, S. Humphrys electronically filed by Docketing Staff.
07/21/2017 Application (Part 9) Exhibit 6-2 for the Dowling-Midway 138kV Transmission Line Reconductor Project filed by FirstEnergy, S. Humphrys electronically filed by Docketing Staff.
07/21/2017 Application (Part 9) Exhibit 6-1 for the Dowling-Midway 138kV Transmission Line Reconductor Project filed by FirstEnergy, S. Humphrys electronically filed by Docketing Staff.
07/21/2017 Application (Part 8) for the Dowling-Midway 138kV Transmission Line Reconductor Project filed by FirstEnergy, S. Humphrys electronically filed by Docketing Staff.
07/21/2017 Application (Part 7) for the Dowling-Midway 138kV Transmission Line Reconductor Project filed by FirstEnergy, S. Humphrys electronically filed by Docketing Staff.
07/21/2017 Application (Part 6) for the Dowling-Midway 138kV Transmission Line Reconductor Project filed by FirstEnergy, S. Humphrys electronically filed by Docketing Staff.
07/21/2017 Application (Part 5) for the Dowling-Midway 138kV Transmission Line Reconductor Project filed by FirstEnergy, S. Humphrys electronically filed by Docketing Staff.
07/21/2017 Application (Part 4) for the Dowling-Midway 138kV Transmission Line Reconductor Project filed by FirstEnergy, S. Humphrys electronically filed by Docketing Staff.
07/21/2017 Application (Part 3) for the Dowling-Midway 138kV Transmission Line Reconductor Project filed by FirstEnergy, S. Humphrys electronically filed by Docketing Staff.
07/21/2017 Application (Part 2) for the Dowling-Midway 138kV Transmission Line Reconductor Project filed by FirstEnergy, S. Humphrys electronically filed by Docketing Staff.
07/21/2017 Application (Part 1) for the Dowling-Midway 138kV Transmission Line Reconductor Project filed by FirstEnergy, S. Humphrys electronically filed by Docketing Staff.
07/21/2017 Pre-Application notification letter Dowling-Midway 138 kV Transmission Line Reconductor Project filed by Scott Humphrys on behalf of FirstEnergy Service Company.
07/19/2017 In the matter of the Notice of the Filing of the Pre-Application Letter for Project electronically filed by Mr. Robert J. Schmidt on behalf of American Transmission Systems Inc.