12/10/2018
|
Letter of Notification and Construction Notice stating that the projects were completed on November 30, 2018 filed by N. Bryksenkova. on behalf of FirstEnergy Service Company. |
02/26/2018
|
Letter of Notification that project will commence on 2/22/2018 filed by Nataliya Bryksenkova on behalf of FirstEnergy Service Company. |
04/28/2017
|
Notification of Public Information Meeting electronically filed by Mr. Robert J Schmidt on behalf of American Transmission Systems Inc. |
04/07/2017
|
Staff Report of Investigation electronically filed by Mr. Jason Cross on behalf of Siting Staff. |
04/07/2017
|
Notice of the Filing of Supplemental Information for Application electronically filed by Mr. Robert J Schmidt on behalf of American Transmission Systems Inc. |
04/07/2017
|
Service Notice |
03/17/2017
|
Letter of Notification concerning the Clark-Urbana 138 kV Loop to Broadview Substation Project filed by Nataliya Bryksenkova on behalf of FirstEnergy Service Company. |
01/20/2017
|
Proof of Public Notice of the Filing of the Application electronically filed by Mr. Robert J Schmidt on behalf of American Transmission Systems Inc. |
01/13/2017
|
Letter of Notification Clark-Urbana 138 kV Loop to Broadview Substation Expansion Case No. 16-2282-EL-BLN filed by Nataliya Bryksenkova on behalf of FirstEnergy Service Company. |
01/10/2017
|
Notice of Change in Application Format and Docket Number electronically filed by Mr. Robert J Schmidt on behalf of American Transmission Systems Inc. |
12/30/2016
|
In the matter of the pre-application notification letter, Clark-Urban 138kV Loop to Broadview Substation Project. |