02/21/2017
|
Notification of Start of Construction and In-Service Date for the Rutland Substation Expansion Project
electronically filed by Mrs. Erin C. Miller on behalf of AEP Ohio Transmission Company. |
08/30/2016
|
Proof of Pub electronically filed by Mr. Hector Garcia on behalf of AEP Ohio Transmission Company. |
08/22/2016
|
Staff Report of Investigation electronically filed by Mrs. Yvonne W Cooper on behalf of Staff of OPSB. |
08/19/2016
|
In the Matter of the Pre-App Notification Ltr re Flag City 138kV T-Line Proj electronically filed by Mrs. Erin C Miller on behalf of AEP Ohio Transmission Company. |
08/04/2016
|
Public Notification Compliance Filing (Rutland) electronically filed by Mr. Hector Garcia on behalf of AEP Ohio Transmission Company. |
08/04/2016
|
Officials Notification Compliance Filing (Rutland) electronically filed by Mr. Hector Garcia on behalf of AEP Ohio Transmission Company. |
08/01/2016
|
Letter of Notification requesting Expedited Treatment electronically filed by Mrs. Erin C Miller on behalf of AEP Ohio Transmission Company. |
08/01/2016
|
Letter of Notification requesting for Expedited Treatment electronically filed by Mrs. Erin C Miller on behalf of AEP Ohio Transmission Company. |
08/01/2016
|
Letter of Notification requesting Expedited Treatment electronically filed by Mrs. Erin C Miller on behalf of AEP Ohio Transmission Company. |
08/01/2016
|
Letter of Notification requesting Expedited Treatment electronically filed by Mrs. Erin C Miller on behalf of AEP Ohio Transmission Company. |
08/01/2016
|
Letter of Notification requesting Expedited Treatment electronically filed by Mrs. Erin C. Miller on behalf of AEP Ohio Transmission Company. |
07/26/2016
|
In the matter of the Letter of Notification for the Rutland Substation Expansion Project electronically filed by Mrs. Erin C. Miller on behalf of AEP Ohio Transmission Company. |