08/09/2019
|
Case Action Form Close Cases as of 8/9/2019 electronically filed by Ms. Mary E Fischer on behalf of Jeffrey R. Jones, Attorney Examiner, Public Utilities Commission of Ohio. |
02/09/2017
|
Notification of Start of Construction and In-Service Date for the Hanging Rock 138 kV Transmission Line Project electronically filed by Mrs. Erin C Miller on behalf of AEP Ohio Transmission Company. |
08/30/2016
|
Proof of Pub electronically filed by Mr. Hector Garcia on behalf of AEP Ohio Transmission Company. |
08/22/2016
|
Correspondence regarding the Acceptance of Staff's Conditions (Hanging Rock) electronically filed by Mrs. Erin C Miller on behalf of AEP Ohio Transmission Company. |
08/19/2016
|
Staff Report of Investigation electronically filed by Mrs. Yvonne W Cooper on behalf of Staff of OPSB. |
08/03/2016
|
Public Notification Compliance Filing (Hanging Rock) electronically filed by Mr. Hector Garcia on behalf of AEP Ohio Transmission Company. |
08/03/2016
|
Officials Notification Compliance Filing (Hanging Rock) electronically filed by Mr. Hector Garcia on behalf of AEP Ohio Transmission Company. |
08/02/2016
|
Correction Letter electronically filed by Mrs. Erin C Miller on behalf of AEP Ohio Transmission Company. |
07/29/2016
|
Letter of Notification Part 13 of 13 electronically filed by Mrs. Erin C. Miller on behalf of AEP Ohio Transmission Company. |
07/29/2016
|
Letter of Notification Part 12 of 13 electronically filed by Mrs. Erin C. Miller on behalf of AEP Ohio Transmission Company. |
07/29/2016
|
Letter of Notification Part 11 of 13 electronically filed by Mrs. Erin C. Miller on behalf of AEP Ohio Transmission Company. |
07/29/2016
|
Letter of Notification Part 10 of 13 electronically filed by Mrs. Erin C. Miller on behalf of AEP Ohio Transmission Company. |
07/29/2016
|
Letter of Notification Part 9 of 13 electronically filed by Mrs. Erin C. Miller on behalf of AEP Ohio Transmission Company. |
07/29/2016
|
Letter of Notification Part 8 of 13 electronically filed by Mrs. Erin C. Miller on behalf of AEP Ohio Transmission Company. |
07/29/2016
|
Letter of Notification Part 7 of 13 electronically filed by Mrs. Erin C. Miller on behalf of AEP Ohio Transmission Company. |
07/29/2016
|
Letter of Notification Part 6 of 13 electronically filed by Mrs. Erin C. Miller on behalf of AEP Ohio Transmission Company. |
07/29/2016
|
Letter of Notification Part 5 of 13 electronically filed by Mrs. Erin C. Miller on behalf of AEP Ohio Transmission Company. |
07/29/2016
|
Letter of Notification Part 4 of 13 electronically filed by Mrs. Erin C. Miller on behalf of AEP Ohio Transmission Company. |
07/29/2016
|
Letter of Notification Part 3 of 13 electronically filed by Mrs. Erin C. Miller on behalf of AEP Ohio Transmission Company. |
07/29/2016
|
Letter of Notification Part 2 of 13 electronically filed by Mrs. Erin C. Miller on behalf of AEP Ohio Transmission Company. |
07/29/2016
|
Letter of Notification Part 1 of 13 electronically filed by Mrs. Erin C. Miller on behalf of AEP Ohio Transmission Company. |
07/18/2016
|
In the Matter of the Pre-Application Notification Letter electronically filed by Mrs. Erin C Miller on behalf of AEP Ohio Transmission Company. |