Date Filed | Summary | Pages |
08/07/2019 | Case Action Form Closing Cases with an effective date of 8/7/19 electronically filed by Ms. Mary E Fischer on behalf of Jeffrey R. Jones, Attorney Examiner, Public Utilities Commission of Ohio. | 2 |
11/13/2017 | Notification electronically filed by Ms. Christen M. Blend on behalf of AEP Ohio Transmission Power Company, Inc. | 2 |
02/09/2017 | Notification of Start of Construction for the Yager-Leesville 138 kV Transmission Line Project electronically filed by Mrs. Erin C Miller on behalf of AEP Ohio Transmission Company. | 2 |
09/09/2016 | Correspondence - Accepting all Staff Conditions (Yager-Leesville electronically filed by Mr. Hector Garcia on behalf of AEP Ohio Transmission Company. | 2 |
09/06/2016 | Staff Report of Investigation electronically filed by Mr. Matt Butler on behalf of Staff of OPSB. | 5 |
08/31/2016 | Proof of Pub electronically filed by Mr. Hector Garcia on behalf of AEP Ohio Transmission Company. | 5 |
08/16/2016 | Notification - Officials Notification Compliance Filing (Yager-Leesville) electronically filed by Mr. Hector Garcia on behalf of AEP Ohio Transmission Company | 2 |
08/16/2016 | Public Notification Compliance Filing (Yager-Leesville) electronically filed by Mr. Hector Garcia on behalf of AEP Ohio Transmission Company | 2 |
08/12/2016 | Letter of Notification electronically filed by Mrs. Erin C Miller on behalf of AEP Ohio Transmission Company. (Part 5 of 5) | 60 |
08/12/2016 | Letter of Notification electronically filed by Mrs. Erin C Miller on behalf of AEP Ohio Transmission Company. (Part 4 of 5) | 38 |
08/12/2016 | Letter of Notification electronically filed by Mrs. Erin C Miller on behalf of AEP Ohio Transmission Company. ( Part 3 of 5) | 20 |
08/12/2016 | Letter of Notification electronically filed by Mrs. Erin C Miller on behalf of AEP Ohio Transmission Company. (Part 2 of 5) | 26 |
08/12/2016 | Letter of Notification Requesting Expedited Treatment for the Yager-Leesville 138kV Transmission Line Project electronically filed by Mrs. Erin C Miller on behalf of AEP Ohio Transmission Company. (Part 1 of 5) | 14 |
08/03/2016 | In the matter of the Pre-Application Notification Letter of AEP Ohio Transmission Company, Inc. for the Yager-Leesville 138kV Transmission Line Project electronically filed by Mrs. Erin C Miller on behalf of AEP Ohio Transmission Company. | 3 |