08/09/2019 | Case Action Form Close Cases as of 8/9/2019 electronically filed by Ms. Mary E Fischer on behalf of Jeffrey R. Jones, Attorney Examiner, Public Utilities Commission of Ohio. | 2 |
11/13/2017 | Notification electronically filed by Ms. Christen M. Blend on behalf of AEP Ohio Transmission Power Company, Inc. | 2 |
02/15/2017 | Notice of Start of Construction and In-Service Date for the Nottingham-Freebyrd 138 kV Transmission Line Project electronically filed by Mrs. Erin C Miller on behalf of AEP Ohio Transmission Company. | 2 |
02/16/2016 | Letter of Notification re Construction Start Date electronically filed by Mr. Hector Garcia on behalf of AEP Ohio Transmission Company. | 2 |
02/02/2016 | Correspondence Accepting Staff's Conditions electronically filed by Mr. Hector Garcia on behalf of AEP Ohio Transmission Company. | 2 |
01/28/2016 | Staff Report of Investigation electronically filed by Mrs. Yvonne W Cooper on behalf of Staff of OPSB. | 6 |
01/21/2016 | Correspondence electronically filed by Mr. Hector Garcia on behalf of AEP Ohio Transmission Company. | 3 |
11/20/2015 | Proof of Pub electronically filed by Mr. Hector Garcia on behalf of AEP Ohio Transmission Company. | 4 |
11/05/2015 | Letter of Notification Part 2 electronically filed by Mr. Hector Garcia on behalf of AEP Ohio Transmission Company. | 78 |
11/05/2015 | In the matter of the Letter of Notification Part 1 electronically filed by Mr. Hector Garcia on behalf of AEP Ohio Transmission Company. | 12 |