09/18/2017
|
Case Action Form closing case with an effective date of 9/18/17, In the matter the PUCO Flasher LED Upgrade Program for Norfolk Southern Corporation electronically filed by Mrs. Jill A. Henry on behalf of PUCO/Rail Division. |
09/18/2017
|
Memo Closing Case with an effective date of 9/18/17, In the matter of the PUCO Flasher LED Upgrade Program for Norfolk Southern Corporation electronically filed by Mrs. Jill A. Henry on behalf of PUCO/Rail Division. |
02/13/2017
|
Service Notice |
02/13/2017
|
Attorney Examiner Entry extending project completion date and directing NS to complete the project by 03/17/2017 - electronically filed by Sandra Coffey on behalf of James Lynn, Attorney Examiner, Public Utilities Commission of Ohio. |
02/08/2017
|
Request for Extension of Project Deadline electronically filed by Mr. D. Casey Talbott on behalf of Norfolk Southern Railway Company. |
01/09/2017
|
Request for Extension of Project Deadline electronically filed by Mr. D. Casey Talbott on behalf of Norfolk Southern Railway Company |
12/12/2016
|
Service Notice |
12/12/2016
|
Attorney Examiner Entry granting NS's request for an extension of time to complete project and directs the project to be completed by 01/16/2017. - electronically filed by Sandra Coffey on behalf of Scott Farkas, Attorney Examiner, Public Utilities Commission of Ohio. |
12/09/2016
|
Response to extension request for the NS LED Upgrade Program. electronically filed by Mrs. Jill A Henry on behalf of PUCO/Rail Division. |
12/08/2016
|
Request for Extension of Project Deadline and memorandum in support electronically filed by Mr. D. Casey Talbott on behalf of Norfolk Southern Railway Company. |
10/07/2016
|
Memorandum Staff Modification of LED Upgrade List for Norfolk Southern Railroad LED Crossing Upgrades electronically filed by Mrs. Jill A Henry on behalf of PUCO/Rail Division. |
11/02/2015
|
Memo informing the Commission that NS has complete the list of the 100 crossing LED upgrades filed by Staff. |
06/17/2015
|
Service Notice |
06/17/2015
|
Finding and order stating that the Stipulation be adopted and approved; Staff file a list of the crossings that will be the subject of LED upgrades by October 31, 2015; NS proceed with and complete the project on or before December 17, 2016. |
06/12/2015
|
Memo stating that Staff has reviewed agreements and have determined them to be in order and requests that an entry adopting the Subsidy Stipulations and requiring completion of upgrades within 18 months filed by Rail Staff, J. Henry. |
06/10/2015
|
In the matter of the PUCO Flasher Upgrade Program for Norfolk Southern Corporation. |