07/01/2019
|
Case Action Form Closing Case with an effective date of 6/28/2019, In the Matter of a Request for the Installation of Active Warning Devices at Wheeling & Lake Erie Railway Grade Crossing, DOT#473-568S, Pawnee Road in Medina County, Ohio. electronically filed by Mrs. Jill A Henry on behalf of PUCO/Rail Division. |
07/01/2019
|
Memo Closing Case In the Matter of a Request for the Installation of Active Warning Devices at Wheeling & Lake Erie Railway Grade Crossing, DOT#473-568S, Pawnee Road in Medina County, Ohio. electronically filed by Mrs. Jill A Henry on behalf of PUCO/Rail Division. |
07/28/2016
|
Attorney Examiner Entry granting WE's request for additional time to complete the project no later than 08/20/2016, directing WE to notify Staff, ORDC, and the Medina County Commissioners upon the completion of the project, and directing Staff to file a memorandum in this docket indicating that the project has been completed once Staff or ORDC makes its final inspection and finds that the project was completed - electronically filed by Sandra Coffey on behalf of James Lynn, Attorney Examiner, Public Utilities Commission of Ohio. |
07/28/2016
|
Service Notice |
07/22/2016
|
Staff Response to Project Extension Request for Pawnee Road electronically filed by Mrs. Jill A Henry on behalf of PUCO/Rail Division. |
07/19/2016
|
Request for extension of time filed by T. Andrews on behalf of Wheeling & Lake Erie Railway Co. |
06/23/2016
|
Service Notice |
06/23/2016
|
Attorney Examiner Entry ordering WE’s request for additional time to complete the project, no later than July 20, 2016, is granted in accordance with paragraph 6; that WE notify Staff, the Ohio Rail Development Commission (ORDC), and Medina County upon the completion of the project; and that, when Staff or ORDC makes its final inspection and finds that the project is completed in accordance with the agreement, Staff file a memorandum in this docket indicating that the project is completed - electronically filed by Debra Hight on behalf of Scott E. Farkas, Attorney Examiner. |
06/22/2016
|
Staff Response to Project Extension Request for Pawnee Road by Wheeling & Lake Erie Railroad electronically filed by Mrs. Jill A Henry on behalf of PUCO/Rail Division. |
06/16/2016
|
Request for an extension of time file by T. Andrews on behalf of Wheeling & Lake Erie Railway Company. |
06/01/2016
|
Attorney Examiner Entry granting WE's request for additional time to complete project in accordance with paragraph 5. - electronically filed by Sandra Coffey on behalf of James Lynn, Attorney Examiner, Public Utilities Commission of Ohio |
06/01/2016
|
Service Notice |
05/24/2016
|
Staff Response to Pawnee Road Project Extension Request electronically filed by Mrs. Jill A Henry on behalf of PUCO/Rail Division |
05/19/2016
|
Request to extend the deadline for an additional 30 days to complete project filed by T. Andrews on behalf of Wheeling & Lake Erie Railway Company. |
01/25/2016
|
Memorandum that the plans and estimates submitted by WE have been reviewed and authorization is recommended filed by PUCO Staff. |
05/20/2015
|
Service Notice |
05/20/2015
|
Finding and Order that the stipulation be adopted and approved. |
04/27/2015
|
In the matter of the Request for the Installation of Active Warning Devices at Wheeling & Lake Erie Railway Grade Crossing DOT #473-568S, Pawnee Road in Medina County, Ohio. |