09/13/2019
|
Case Action Form to Close Case with and effective date of 9/13/2019 electronically filed by Ms. Mary E Fischer on behalf of Jeffrey R. Jones, Administrative Law Judge, The Ohio Power Siting Board. |
09/07/2017
|
Notice electronically filed by Mr. Hector Garcia on behalf of AEP Ohio Transmission Company. |
02/09/2017
|
Notification of Start of Construction for the Poston-Hocking 138 kV Transmission Line Project electronically filed by Mrs. Erin C Miller on behalf of AEP Ohio Transmission Company. |
09/28/2015
|
Response electronically filed by Mr. Hector Garcia on behalf of AEP Ohio Transmission Company. |
09/21/2015
|
Proof of Pub electronically filed by Mr. Hector Garcia on behalf of AEP Ohio Transmission Company. |
09/21/2015
|
Staff Report of Investigation electronically filed by Mrs. Yvonne W. Cooper on behalf of Staff of OPSB. |
08/28/2015
|
Letter of Notification Poston Hocking 138 kV Transmission Line Rebuild Project (Part 10 of 10) electronically filed by Mr. Matthew J Satterwhite on behalf of AEP Ohio Transmission Company. |
08/28/2015
|
Letter of Notification Poston Hocking 138 kV Transmission Line Rebuild Project Part 9 of 10 electronically filed by Mr. Matthew J Satterwhite on behalf of AEP Ohio Transmission Company |
08/28/2015
|
Letter of Notification Poston Hocking 138 kV Transmission Line Rebuild Project (Part 8 of 10) electronically filed by Mr. Matthew J Satterwhite on behalf of AEP Ohio Transmission Company. |
08/28/2015
|
Letter of Notification Poston Hocking 138 kV Transmission Line Rebuild Project Part 7 of 10 electronically filed by Mr. Matthew J Satterwhite on behalf of AEP Ohio Transmission Company |
08/28/2015
|
Letter of Notification Poston Hocking 138 kV Transmission Line Rebuild Project Part 6 of 10 electronically filed by Mr. Matthew J Satterwhite on behalf of AEP Ohio Transmission Company |
08/28/2015
|
Letter of Notification Poston Hocking 138 kV Transmission Line Rebuild Project (Part 5 of 10) electronically filed by Mr. Matthew J Satterwhite on behalf of AEP Ohio Transmission Company. |
08/28/2015
|
Letter of Notification Poston Hocking 138 kV Transmission Line Rebuild Project (Part 4 of 10) electronically filed by Mr. Matthew J Satterwhite on behalf of AEP Ohio Transmission Company. |
08/28/2015
|
Letter of Notification Poston Hocking 138 kV Transmission Line Rebuild Project Part 3 of 10 electronically filed by Mr. Matthew J Satterwhite on behalf of AEP Ohio Transmission Company. |
08/28/2015
|
Letter of Notification Poston Hocking 138kV Transmission Line Rebuild Project Part 2 of 10 electronically filed by Mr. Matthew J Satterwhite on behalf of AEP Ohio Transmission Company. |
08/28/2015
|
Letter of Notification of the Poston Hocking 138kV Transmission Line Rebuild (Part 1 of 10) electronically filed by Mr. Matthew J Satterwhite on behalf of AEP Ohio Transmission Company. |
07/17/2015
|
Notice of Withdrawal and Substitution of Counsel electronically filed by Mr. Ajay K Kumar on behalf of AEP Ohio Transmission Company. |
07/09/2015
|
In the matter of the Letter of Notification for the Poston Hocking Project electronically filed by Mr. Ajay K Kumar on behalf of AEP Ohio Transmission Company. |