CASE NUMBER: 15-0098-EL-BNR
CASE DESCRIPTION: Portsmouth Area Structure Relocation Project
DOCUMENT SIGNED ON: 11/22/2024
DATE OF SERVICE: ________________________________________
08/09/2019 Case Action Form Close Cases as of 8/9/2019 electronically filed by Ms. Mary E Fischer on behalf of Jeffrey R. Jones, Attorney Examiner, Public Utilities Commission of Ohio.
01/22/2018 Notification of Construction Completion/In-Service Date electronically filed by Ms. Christen M. Blend on behalf of AEP Ohio Transmission Power Company, Inc.
07/17/2015 Notice of Withdrawal and Substitution of Counsel electronically filed by Mr. Ajay K Kumar on behalf of AEP Ohio Transmission Company.
07/10/2015 Notice -Construction Notice for Portsmouth Area Structure Relocation Project electronically filed by Mr. Ajay K Kumar on behalf of AEP Ohio Transmission Company.
02/13/2015 Response, accepting Staff-recommended conditions electronically filed by Mr. Ajay K. Kumar on behalf of AEP Ohio Transmission Company.
02/09/2015 Staff Report of Investigation electronically filed by Mrs. Yvonne W Cooper on behalf of Staff of OPSB.
01/26/2015 In the matter of the Construction Notice for Portsmouth Area Structure Relocation Project electronically filed by Mr. Ajay K. Kumar on behalf of AEP Ohio Transmission Company.