CASE NUMBER: 14-2161-EL-BLN
CASE DESCRIPTION: Babb-East Akron/Aetna (West Akron) 138kV Structure Replacement Project
DOCUMENT SIGNED ON: 7/17/2024
DATE OF SERVICE: ________________________________________
04/24/2015 Notice of completion of project filed by N. Bryksenkova on behalf of FiirstEnergy Service Company.
02/23/2015 Response letter to the Letter of Notification that the construction on this project is set to begin on approximately February 25, 2015, filed by N. Bryksenkova on behalf of FirstEnergy Service Company.
12/29/2014 Proof of Publication for the County of Summit filed by R. Schmidt, Jr, ATSI.
12/11/2014 Staff Report of Investigation electronically filed by Mrs. Yvonne W Cooper on behalf of Staff of OPSB.
12/05/2014 In the matter of the letter of notification of American Transmission System Incorporated for the Babb-East Akron / Aetna (West Akron) 138 kV Transmission Line Structure Replacement Project.