08/09/2019 Case Action Form Close Cases as of 8/9/2019 electronically filed by Ms. Mary E Fischer on behalf of Jeffrey R. Jones, Attorney Examiner, Public Utilities Commission of Ohio.
02/15/2017 Notice of Start of Construction and In-Service Date for the Nottingham Substation Project electronically filed by Mrs. Erin C Miller on behalf of AEP Ohio Transmission Company.
07/17/2015 Notice of Withdrawal and Substitution of Counsel electronically filed by Mr. Ajay K Kumar on behalf of AEP Ohio Transmission Company.
07/10/2015 Letter of Notification for Nottingham Substation Project electronically filed by Mr. Ajay K Kumar on behalf of AEP Ohio Transmission Company.
12/30/2014 Correspondence electronically filed by Mr. Ajay K Kumar on behalf of AEP Ohio Transmission Company.
12/11/2014 Staff Report of Investigation electronically filed by Mrs. Yvonne W Cooper on behalf of Staff of OPSB.
12/08/2014 Proof of Pub Nottingham Substation Project electronically filed by Mr. Ajay K Kumar on behalf of AEP Ohio Transmission Company.
11/21/2014 In the matter of the Letter of Notification electronically filed by Mr. Matthew J Satterwhite on behalf of AEP Ohio Transmission Company.