07/17/2015
|
Notice of Withdrawal and Substitution of Counsel electronically filed by Mr. Ajay K Kumar on behalf of AEP Ohio Transmission Company. |
07/10/2015
|
Notice -Construction Notice for Hazelton 138 kV Transmission Line Tap Project electronically filed by Mr. Ajay K Kumar on behalf of AEP Ohio Transmission Company. |
10/15/2014
|
Staff Report of Investigation electronically filed by Mrs. Yvonne W Cooper on behalf of Staff of OPSB. |
09/11/2014
|
In the matter of the notification for the construction of Hazelton 138kv Transmission Line Tap Project electronically filed by Mr. Yazen Alami on behalf of AEP Ohio Transmission Company. |