07/06/2015
|
Construction Notice that the construction was considered complete on October 23, 2014. filed by William R. Beutler on behalf of FirstEnergy Service Company. |
11/10/2014
|
Correspondence letter in response to Construction notice stating construction was completed on October 23, 2014 filed on behalf of FirstEnergy Service Company by J. Thacker. |
10/10/2014
|
Staff Report of Investigation electronically filed by Mrs. Yvonne W Cooper on behalf of Staff of OPSB. |
09/09/2014
|
In the matter of the Construction Notice Wadsworth Muni Silvercrest-West Akron 138kV Transmission Line By-Pass at Pine Substation Project. |