DIS - Case Record for 14-1085-EL-BNR Skip to main content
      
      
CASE NUMBER: 14-1085-EL-BNR
CASE DESCRIPTION: American Transmission Systems, Incorporated/Avon-Fowles Q1 and Q3 138 kV Transmission Lines Dual Tap to Bentley Substation Project
DOCUMENT SIGNED ON: 4/18/2024
DATE OF SERVICE: ________________________________________
07/20/2015 Notice of construction completion filed by J. Thacker on behalf of FirstEnergy Service Corporation.
07/06/2015 Letter of Notification for the Avon-Fowles Q1 and Q3 138 kV Transmission Lines Dual Tap to Bentley Substation filed on behalf of FirstEnergy by J. Thacker.
10/23/2014 Response to construction notice informing project will begin week of October 27, 2014 and notification will be given once completed filed by J. Thacker on behalf of FirstEnergy Service Company.
07/24/2014 Staff Report of Investigation electronically filed by Mr. Matt Butler on behalf of Staff of OPSB.
07/15/2014 Construction notice containing exhibits that were inadvertently left out of the original filing filed on behalf of FirstEnergy service Company by J. Toth.
06/18/2014 In the matter of the letter of notification of American Transmission Systems, Incorporated for the Avon-Fowles 138 kV Transmission Lines Dual Tap to Bentley Substation Project.