Date Filed | Summary | Pages |
07/17/2015 | Notice of Withdrawal and Substitution of Counsel electronically filed by Mr. Ajay K Kumar on behalf of AEP Ohio Transmission Company. | 3 |
06/18/2015 | Notice -Construction Notice for Krammer West Bellaire 345 kV Circuit Re-conductor Project electronically filed by Mr. Ajay K Kumar on behalf of AEP Ohio Transmission Company. | 2 |
02/12/2014 | Correspondence accepting Staff-recommended conditions electronically filed by Mr. Yazen Alami on behalf of AEP Ohio Transmission Company. | 2 |
02/11/2014 | Report of investigation electronically filed by Mr. Adam S. Bargar on behalf of Staff of OPSB. | 4 |
02/05/2014 | Correspondence clarifying project need electronically filed by Mr. Yazen Alami on behalf of AEP Ohio Transmission Company. | 2 |
01/08/2014 | In the Matter of the Notice of Construction of the Kammer-West Bellaire 345kV Circuit Re-conductor Project electronically filed by Mr. Yazen Alami on behalf of AEP Ohio Transmission Company. | 21 |