07/17/2015 | Notice of Withdrawal and Substitution of Counsel electronically filed by Mr. Ajay K Kumar on behalf of AEP Ohio Transmission Company. | 3 |
06/04/2015 | Construction notice stating that the Melmore-Tiffin 138 kV Transmission Line Project was completed on December 12, 2014 electronically filed by Mr. Ajay K. Kumar on behalf of AEP Ohio Transmission Company. | 2 |
01/10/2014 | Correspondence accepting the Staff Recommended Conditions electronically filed by Mr. Yazen Alami on behalf of AEP Ohio Transmission Company. | 2 |
01/08/2014 | Report of Investigation, electronically filed by Mr. Adam S Bargar on behalf of Staff of OPSB. | 5 |
11/19/2013 | Proof of Pub for Melmore-Tiffin Center electronically filed by Mr. Yazen Alami on behalf of AEP Ohio Transmission Company. | 4 |
10/29/2013 | Application letter of Notification Part 3 of 3- Melmore-Tiffin Center 138k V line Improvement Project electronically filed by Mr. Yazen Alami on behalf of AEP Ohio Transmission Company | 46 |
10/29/2013 | Application letter of Notification Part 2 of 3- Melmore-Tiffin Center 138k V Line Improvement Project electronically filed by Mr. Yazen Alami on behalf of AEP Ohio Transmission Company | 44 |
10/29/2013 | In the matter of the Letter of Notification Part 1 of 3- Melmore-Tiffin Center 138k V Line Improvement Project electronically filed by Mr. Yazen Alami on behalf of AEP Ohio Transmission Company | 21 |