Date Filed | Summary | Pages |
08/30/2013 | Letter stating that construction on Chrysler-Maclean 138 kV Transmission Line Switch Structure Replacement Project was completed on approximately July 15, 2013 filed by S. Humphrys on behalf of FirstEnergy Service Company. | 1 |
05/30/2013 | Report of investigation electronically filed by Mr. Adam S Bargar on behalf of Staff of OPSB. | 3 |
05/10/2013 | Letters of notification, servicing the Chrysler-Maclean project filed by S. Humphrys, FirstEnergy Service Company. | 12 |
05/10/2013 | In the matter of the Letter of Notification , Chrysler-Maclean 138kV Transmission Line Switch Structure Replacement Project. | 14 |
|