Date Filed | Summary | Pages |
11/10/2014 | Correspondence letter in response to the Construction Notice stated project was completed on October 23, 2014 filed on behalf of FirstEnergy Service Company by J. Thacker. | 1 |
05/22/2013 | Letter in response to Ohio Administrative Code § 4906-5-02(A)(5), please be advised that the construction on this project began on May 17, 2013. Filed by Jessica Thacker on behalf of FirstEnergy Service Company. | 1 |
05/08/2013 | Report of investigation electronically filed by Mr. Adam S Bargar on behalf of Staff of OPSB. | 3 |
05/02/2013 | Correspondence stating that American Transmission Systems, Inc. and Ohio Edison Company, FirstEnergy Companies have submitted a payment of $2000.00 so that the Construction Notice may be reviewed on an expedited basis filed by J. Thacker. | 1 |
04/24/2013 | Letters informing of Wadsworth Muni Silvercrest-West Akron 138 kV Transmission Line Temporary By-Pass at Pine Substation Project filed by J. Thacker on behalf of American Transmission Systems, Inc. | 10 |
04/24/2013 | In the matter of notification of American Transmission Systems, Inc. for the Wadsworth Silvercrest-West Akron 138kV Transmission line temporary by-pass at Pine Sub. | 10 |