Date Filed | Summary | Pages |
07/17/2015 | Notice of Withdrawal and Substitution of Counsel electronically filed by Mr. Ajay K Kumar on behalf of AEP Ohio Transmission Company. | 3 |
06/04/2015 | Construction Notice stating that the Poston Elliott 138 kV Reconducter Rebuild Project was completed on May 2, 2014 electronically filed by Mr. Ajay K. Kumar on behalf of AEP Ohio Transmission Company. | 2 |
04/15/2013 | Notice -Construction Notice of Acceptance of Conditions-Poston Elliott 138 kV Line electronically filed by Erin C Miller on behalf of AEP Ohio Transmission Company, Inc. | 2 |
04/04/2013 | Report of investigation electronically filed by Mr. Adam S Bargar on behalf of Staff of OPSB. | 5 |
02/28/2013 | In the matter of the Construction notice for the Poston - Elliott 138kV Line (Reconductor/Rebuild Project) electronically filed by Mr.Yazen Alami on behalf of AEP Ohio Transmission Company. | 8 |