07/10/2013
|
Response to the Letter of Notification filed by J. Thacker on behalf of FirstEnergy Service Company. |
05/07/2013
|
Staff Report of Investigation electronically filed by Mr. Adam S Bargar on behalf of Staff of OPSB. |
03/26/2013
|
Proof of Pub in the Toledo Blade for Angola-Eber-Vulcan 138 kV Transmission Line Structure Replacement Project filed by Robert J. Schmidt Jr. on behalf of American Transmission Systems, Inc. |
02/21/2013
|
Service notice for Angola-Eber-Vulcan Transmission Line Project filed by J. Thacker on behalf of EDTS. |
02/21/2013
|
In the matter of the letter of notification Angola-Eber-Vulcan 138 kV Transmission Line Structure Replacement Project. |