07/25/2014
|
Correspondence that the Avery-Greenfield 138kV Transmission Line Extension to Hayes Substation was placed in service May 15, 2014 and construction completed approximately June 16, 2014 filed by S. Humphrys on behalf of FirstEnergy. |
01/31/2013
|
Report of investigation electronically filed by Mr. Adam S Bargar on behalf of Staff of OPSB. |
12/07/2012
|
In the matter of the application of the Letter of Notification for Avery-Greenfield 138 kV Transmission Line Extension to Hayes Substation |
|