06/15/2015 | Memo closing case with and effective date of 6/15/2015. | 1 |
11/30/2012 | Letter in response to the Construction Notice for Galion-Roberts 138 kV Transmission Line Tap to US Yachiyo Substation Project filed by J. Toth on behalf of FirstEnergy Service Company. | 1 |
10/01/2012 | Staff investigation report and recommendations submitted on behalf of OPSB Staff, J. O'Dell. | 1 |
08/27/2012 | In the matter of the application of Ohio Edison Company for Gallon-Roberts 138 kV Transmission Line Tap to the US Yachiyo Substation. | 20 |