06/12/2015
|
Response letter stating construction began on October 10, 2012 filed on behalf of FirstEnergy Service Company by W. Beutler. |
05/22/2013
|
Letter in response to Ohio Administrative Code ยง 4906-5-02(B)(6),
please be advised that construction on this project was completed on approximately May 17, 2013. Filed by John T. Toth on behalf of FirstEnergy Service Company. |
09/05/2012
|
Staff Investigation Report and Recommendation filed by OPSB Staff. |
08/01/2012
|
In the matter of the application/construction notice of American Transmission Systems, Incorporated, the Hanna-West Ravenna #1 & #2 double circuit 138 kV reconductor project. |
|