DIS - Case Record for 10-2439-EL-BSB Skip to main content
      
      
CASE NUMBER: 10-2439-EL-BSB
CASE DESCRIPTION: CITY OF HAMILTON/AMERICAN MUNICIPAL POWER
DOCUMENT SIGNED ON: 11/22/2024
DATE OF SERVICE: ________________________________________
12/04/2017 Case action form closing cases with an effective date of 12/4/17 electronically filed by Mr. Jeffrey R. Jones on behalf of Public Utilities Commission of Ohio.
03/02/2017 Notice of withdrawal of John W. Bentine; substitute with Kristin V. Rothey, Assistant Deputy General Counsel, FERC/RTO Affairs with American Municipal Power, Inc., as Counsel of Record. electronically filed by Barbara E Johnson on behalf of American Municipal Power, Inc.
06/10/2016 Service Notice
06/10/2016 Administrative Law Judge Entry granting motion for protective treatment of information that was filed on May 24, 2016 and to maintain under seal the information, indefinitely, until otherwise ordered by the Commission; electronically filed by Vesta R Miller on behalf of Mandy Willey Chiles, Administrative Law Judge, Ohio Power Siting Board
05/24/2016 Motion for protective order and memorandum in support filed by M. Kyser on behalf of American Municipal Power, Inc.
01/28/2016 Notice of construction completion and commercial operation for the 138 kV transmission line and associated substation for the Meldahl Hydroelectric Power Project electronically filed by Errin C Harris on behalf of American Municipal Power, Inc.
09/12/2013 Public comment response to Rita Kinne from OPSB Staff, S. Irwin.
03/12/2013 Withdrawal of Joint Motion for Protective Treatment electronically filed by Barbara E Johnson on behalf of American Municipal Power, Inc.
03/04/2013 Notice of construction commencement effective March 4, 2013 filed by A. Bott on behalf of the City of Hamilton.
03/01/2013 Response to D. Garvey, P.E., filed by PUCO Staff.
02/20/2013 Notice of Appearance of Counsel - Lisa G. McAlister with American Municipal Power, Inc. electronically filed by Barbara E Johnson on behalf of American Municipal Power, Inc.
02/19/2013 Confidential target: Detailed Engineering drawings field by Lisa G. McAlister on behalf of American Municipal Power Inc. (111 pages)
02/19/2013 Joint Motion for Protective order and Memorandum in Support filed by Lisa McAllister on behalf of American Municipal Power, Inc and James McLean on behalf of Duke Energy Ohio, Inc and April Bott on behalf of the City of Hamilton, Ohio.
01/28/2013 Notice of Information Provided to Ohio Power Siting Staff filed by April Bott Esq. on behalf of the City of Hamilton.
11/28/2012 Letter on behalf of of the City of Hamilton and American Municipal Power, Inc. asking the Commission to please accept for filing in the docket this Notice that a Baseline TV Reception and Signal Strength Study has been submitted to OPSB staff members, in conformance with the Certificate of Environmental Compatibility and Public Need issued November 28, 2011 filed by A.R. Bott.
08/29/2012 Additional information provided for the City of Hamilton and American Municipal Power, Inc. project filed by A. Bott.
06/07/2012 Notice of regulatory approval filed by A. Bott on behalf of the City of Hamilton.
06/07/2012 Notice of regulatory approval filed by A.Bott on behalf of the City of Hamilton.
04/06/2012 Notice of change of address of John Bentine filed on behalf of American Municipal Power, Inc. by M. Yurick.
01/24/2012 Service notice.
01/23/2012 Entry ordered, that the Browns, the Hacks, and Ms. Adkins are denied leave to file applications for rehearing. It is, further, ordered, that the petitions for leave to intervene filed by Browns, the Hacks, and Ms. Adkins are denied.
01/23/2012 Memorandum in support of Petition for Rehearing filed by R. Uhle Jr. on behalf of petitioners.
01/20/2012 Memorandum In Support of Application for Rehearing electronically filed by Mr. Richard B. Uhle on behalf of Brown, Duane Mr. and Hack, Stephen E. Mr. and Brown, Bethany Mrs. and Hack, Gabrae Mrs. and Adkins, Easter Mrs. and Hack, Michael E. Mr..
01/20/2012 Memorandum In Support of Application for Rehearing electronically filed by Mr. Richard B. Uhle on behalf of Brown, Duane Mr. and Hack, Stephen E. Mr. and Brown, Bethany Mrs. and Hack, Gabrae Mrs. and Adkins, Easter Mrs. and Hack, Michael E. Mr.
01/05/2012 Service Notice
01/05/2012 Entry ordered, that the applications for rehearing filed on behalf of Duane R. Brown and Bethany L. Brown, Gabrae L. Hack, Stephen E. Hack, Michael E. Hack, and Easter A. Adkins, are granted for the purpose of affording the Board additional time to consider the issues raised therein. (MLW)
01/03/2012 Memorandum contra petition for leave in intervene of Gabrae L. Hack and Stephen E. Hack and notice of appeal and application for rehearing by City of Hamilton and American Municipal Power, Inc. filed by April Bott on behalf of City of Hamilton and John Bentine on behalf of American Municipal Power.
01/03/2012 Memorandum Contra petition for leave to intervene of Michael E. Hack and Notice of Appeal and application for rehearing by City of Hamilton and American Municipal Power, Inc filed by April Bott on behalf of City of Hamilton and John Bentine on behalf of American Municipal Power.
01/03/2012 Memorandum Contra petition for leave to intervene of Easter A. Adkins and notice of appeal and application for rehearing by City of Hamilton and American Municipal Power, Inc. filed by April Bott on behalf of City of Hamilton and John Bentine on behalf of American Municipal Power.
01/03/2012 Memorandum Contra petition for leave to intervene of Duane R. Brown and Bethany L. Brown and Notice of appeal and application for rehearing by City of Hamilton and American Municipal Power, Inc. filed by April Bott on behalf of City of Hamilton and John Bentine on behalf of American Municipal Power.
12/23/2011 Application for rehearing and notice of appeal on behalf of Easter A. Adkins, filed by R. Uhle, Jr.
12/23/2011 Petition for leave to intervene and memorandum in support of Easter A. Adkins, filed by R. Uhle, Jr.
12/23/2011 Application for rehearing and notice of appeal of the decision rendered on November 28, 2011 filed on behalf of Michael Hack filed by R. Uhle Jr.
12/23/2011 Petition for leave to intervene and memorandum in support filed on behalf of Michael E. Hack filed by R. Uhle.
12/23/2011 Application for rehearing and notice of appeal of decision rendered on November 28, 2011 filed on behalf of Gabrae and Stephen Hack filed by R. Uhle Jr.
12/23/2011 Petition for leave to intervene of Gabrae L. Hack and Stephen Hack and memorandum in support filed on behalf of Gabrae L. Hack, and Stephen E. Hack, filed by R. Uhle Jr.
12/21/2011 Application for rehearing and appeal of decision filed on behalf of Duane R. Brown and Bethany L. Brown filed by R. Uhle.
12/21/2011 Petition for leave to intervene and memorandum in support filed on behalf of Duane R. Brown and Bethany L. Brown by R. Uhle.
11/29/2011 Service notice.
11/28/2011 Opinion and order and certificates - that the Stipulation filed by the parties is approved and adopted, the certificates be issued to Applicants, and the certificates contain the 50 conditions set forth in Section V of this order.
11/23/2011 Transcript of the City of Hamilton and American Municipal Power, Inc. hearing held on 11/03/11 electronically filed by Mrs. Jennifer Duffer on behalf of Armstrong & Okey, Inc. and Dillion, Iris I. Mrs.
11/21/2011 PUCO exhibit filing for hearing held 11/03/11.
11/08/2011 Transcript to the testimony of PUCO hearing held on 10/13/11 in Felicity, Ohio.
11/03/2011 Notice of Withdrawal filed by Thomas J. Ruwe.
11/01/2011 Joint Stipulation and Recommendation filed by Steven L. Beeler and Christina E. Garasseschi on behalf of Staff of the Ohio Power Siting Board, April R. Bott on behalf of The City of Hamilton, and John W. Bentine on behalf of American Municipal Power, Inc.
10/31/2011 Prefiled Testimony of Steven E. Malone Ohio Environmental Protection Agency on behalf of the Staff of the Ohio Power Siting Board filed by Steven L. Beeler.
10/31/2011 Prefiled testimony of Donald E. Rostofer of the Energy & Environment Department Efficiency & Renewables division on behalf of the Staff of the Ohio Power Siting Board.
10/31/2011 Prefiled testimony of Jon C. Pawley Energy & Environment Department Facilities, siting, & Environemtnal Analysts division on behalf of the Staff of the Ohio Power Siting Board filed by Steven L. Beeler.
10/24/2011 Public comment of Stephen and Gabrae Hack concerning the Hamilton/AMP Meldahl Transmission Line and Substation Project.
10/20/2011 Service Notice
10/20/2011 Entry ordered that the joint motion for a continuance of the evidentiary hearing and the extension of the deadline for filing expert and factual testimony be granted , ordered that the evidentiary hearing be continued from October 25, 2011, to November 3, 2011, as set forth in Finding (6). It is, further, ordered that the deadline for expert and factual testimony to be offered by intervenor and Staff be extended from October 20,2011, to October 31, 2011. as set forth in Finding (6) (SF)
10/19/2011 Service Notice
10/18/2011 Joint motion for continuance and extension of the deadline to file staff testimony filed on behalf of the City of Hamilton by A. Bott and American Municipal Power, Inc. by J. Bentine.
10/17/2011 Entry ordered: that in accordance with Finding (6), Applicants' motion for partial waivers be granted. (MLW)
10/13/2011 Service Notice
10/13/2011 Entry ordering that the evidentiary hearing be continued until October 25, 2011, at 10:00 a.m., 11th floor, Hearing Room 11-D, at the offices of the Commission, 180 East Broad Street, Columbus, Ohio 43215-3793; the deadline for expert and factual testimony to be offered by intervenors and Staff be extended until October 20, 2011; parties adhere to the process set forth in Finding (5) (MLW)
10/11/2011 Proof of publication. (Clermont County & Bracken County)
10/06/2011 Direct Testimony of Paul Blaszczyk filed by April Bott on behalf of the City of Hamilton and American Municipal Power Inc.
10/06/2011 Direct Testimony of Mark Brandenburger filed by April Bott on behalf of the City of Hamilton and American Municipal Power Inc.
10/06/2011 Direct Testimony of Phillip A. Meier filed by April Bott on behalf of the City of Hamilton and American Municipal Power Inc.
10/06/2011 Direct Testimony of Jeffrey Boltz Ph.D filed by April Bott on behalf of the City of Hamilton and American Municipal Power Inc.
10/04/2011 Consumer, B. & N. Nutley, in opposition to the Mehldahl project with an attached letter from US Representative Schmidt.
10/04/2011 Service Notice
10/04/2011 Entry ordering that Mr. Eubanks is granted intervention in this matter in accordance with finding (6). (MLW)
10/03/2011 List of Issues filed by John Bentine and April Bott on behalf of City of Hamiltion and American Municipal Power Inc.
09/29/2011 Service Notice
09/28/2011 Staff Report of Investigation electronically filed by T B on behalf of Staff of the Ohio Power Siting Board.
09/27/2011 Letter stating that the Staff does not object to the waiver request filed by Steven L. Beeler.
09/27/2011 Responses to Additional Clarification Questions from OPSB staff filed by April Bott on behalf of the City of Hamilton and American Municipal Power Inc.
09/26/2011 Application for consolidated pending cases 10-2439-EL-BSB and 10-2440-EL-BTX filed by April Bott on behalf of the City of Hamilton and American Municipal Power Inc.
09/26/2011 Motion for waiver and memorandum in support filed by April Bott on behalf of the City of Hamilton and American Municipal Power Inc.
09/16/2011 Correspondence serving as notice that the City of Hamilton and American Municipal Power, Inc. has served notification letters to property owners and public officials as required filed by A. Bott.
09/14/2011 Notice of change of address filed on behalf of the City of Hamilton and American Municipal Power, Inc. by A. Botts.
09/07/2011 Petition for leave to intervene of Lee R. Eubanks and memorandum in support filed by T. Ruwe.
09/02/2011 Correspondence from the Ohio Historic Preservation Office filed on behalf of the City of Hamilton and American Municipal Power, Inc. by A. Bott.
09/02/2011 Response to OPSB staff questions filed by A. Bott.
08/12/2011 Proof of publication; Clermont and Bracken counties filed by A. Bott on behalf of the City of Hamilton and American Municipal Power, Inc.
07/27/2011 Service Notice
07/27/2011 Entry ordering that the motion to consolidate the proceedings in 10-2440 and 10-2439 be granted; the hearings be scheduled at the times and places designated in finding (7); notices of the applications and hearings be published by applicants in accordance with findings(8) and (9); Staff file Staff Report pursuant to finding(10); all parties file their expert and factual testimony in accordance with finding (10). (MLW)
07/19/2011 Letter notifying the Commission that the application fees have been paid to the Fiscal Office on July 19, 2011 filed by A.R. Bott on behalf of the City of Hamilton and American Municipal Power, Inc.
07/14/2011 Letter stating that copies of the complete applications for each case were served in compliance with the requirements filed A.Bott on behalf of the City of Hamilton and American Municipal Power, Inc.
07/07/2011 Correspondence stating that the Staff does not object to the motion to consolidate cases for purpose of investigation and hearing submitted by the City of Hamilton and American Municipal Power, Inc., as agent for Meldahl LLC filed on behalf of PUCO AG Staff, S. Beeler.
07/01/2011 Motion and memorandum in support to consolidate proceedings filed on behalf of the City of Hamilton by A. Bott and J. Bentine.
07/01/2011 Correspondence clarifying certain information contained in the pending application filed May 4, 2011 for a substation associated with the Meldahl Hydroelectric Project filed on behalf of the City of Hamilton and American Municipal Power, Inc. by A. Bott.
07/01/2011 OPSB Letter Regarding Compliance filed by Chairman Todd A. Snitchler on behalf of the Ohio Power Siting Board.
05/04/2011 Application continued. (Part 4)
05/04/2011 Application continued. (Part 3)
05/04/2011 Application Continued. (Part 2)
05/04/2011 In the matter of the Application of the City of Hamilton and American Municipal Power, Inc. for a certificate of environmental compatibility and public need for a 138 kV transmission line and substation project in Franklin and Washington Townships, Clermont County, Ohio. (Part 1)
02/01/2011 Notice of withdrawal of motion for waiver filed A. Bott on behalf of the City of Hamilton and American Municipal Power, Inc..
01/18/2011 Motion for waiver and memorandum in support filed by A. Bott on behalf of the City of Hamilton and J. Bentine on behalf of American Municipal Power-Ohio, Inc.
01/18/2011 Notice of appearance of John W. Bentine on behalf of American Municipal Power Inc, filed by A. Bott.
01/18/2011 Notice of appearance filed by A. Bott on behalf of American Municipal Power Inc.
01/11/2011 Letter giving a broad overview for the City of Hamilton/American Municipal Power, Inc. Meldahl Hydro Project filed by A. Bott.
10/27/2010 In the matter of the application of the City of Hamilton for a new transmission line and substation in Clermont County, Ohio, associated with Hamilton and American Municipal Power, Inc.'s approximately 105 megawatt Meldahl Dam hydroelectric project at the Ohio River.