Date Filed | Summary | Pages |
03/20/2015 | Case Action Form to Close Cases effective 3/20/2015. | 6 |
06/15/2011 | Response to the Construction Notice Bayshore Substation Expansion and 138 kV Bus Tie Project completed on approximately June 6, 2011 filed by J. Thacker on behalf of FirstEnergy Service Company. | 1 |
10/28/2010 | Letter in response to the Construction Notice filed on September 3, 2010 and approved on October 5, 2010 advising that the construction on this project will begin on or shortly after October 21, 2010, filed by J. Thacker. | 1 |
10/05/2010 | OPSB Staff Investigation Report and Recommendation filed. | 1 |
09/03/2010 | In the matter of the construction notice for the Bayshore Substation Expansion and 138 kV J-K Bus Tie Project of FirstEnergy. | 21 |