DIS - Case Record for 10-1017-EL-BLN Skip to main content
      
      
CASE NUMBER: 10-1017-EL-BLN
CASE DESCRIPTION: BEAVER-BROOKSIDE 138 KV TRANSMISSION LINE
DOCUMENT SIGNED ON: 10/7/2024
DATE OF SERVICE: ________________________________________
03/20/2015 Case Action Form to Close Cases effective 3/20/2015.
04/18/2011 Letter of notification advising the Commission that construction on this project was completed on approximately March 18, 2011 filed by J. Thacker on behalf of FirstEnergy Service Company.
09/24/2010 Letter of notification advising that the vegetation clearing portion of the construction will begin on or shortly after October 1, 2010 and the line construction is anticipated to start on March 1, 2011 filed on behalf of FirstEnergy Service Company by J. Thacker.
09/15/2010 Investigation report and recommendation filed by PUCO staff.
07/23/2010 Letter of notification and proof of service of American Transmission Systems, Incorporated for the Beaver-Brookside 138 kV Transmission Line Loop to Henrietta Substation Project filed by J. Thacker.
07/23/2010 In the matter of the application of American Transmission Systems, Inc. proposing to construct a new three steel pole structure an loop on (1) 138kV circuit, the Beaver-Brookside 138kV transmission line into the new Henrietta Substation.