03/20/2015
|
Case Action Form to Close Cases effective 3/20/2015. |
04/18/2011
|
Letter of notification advising the Commission that construction on this project was completed on approximately March 18, 2011 filed by J. Thacker on behalf of FirstEnergy Service Company. |
09/24/2010
|
Letter of notification advising that the vegetation clearing portion of the construction will begin on or shortly after October 1, 2010 and the line construction is anticipated to start on March 1, 2011 filed on behalf of FirstEnergy Service Company by J. Thacker. |
09/15/2010
|
Investigation report and recommendation filed by PUCO staff. |
07/23/2010
|
Letter of notification and proof of service of American Transmission Systems, Incorporated for the Beaver-Brookside 138 kV Transmission Line Loop to Henrietta Substation Project filed by J. Thacker. |
07/23/2010
|
In the matter of the application of American Transmission Systems, Inc. proposing to construct a new three steel pole structure an loop on (1) 138kV circuit, the Beaver-Brookside 138kV transmission line into the new Henrietta Substation. |