02/04/2013
|
Case status form to archive case. |
06/29/2012
|
Memo closing case with an effective date of 6/29/12. |
06/12/2012
|
Memo that the ORDC has completed the final inspection and these cases can be closed. |
03/21/2012
|
Service Notice |
03/21/2012
|
Entry ordering that the W&LE be granted an extension of time until May 1, 2012, to complete all of the projects. |
02/29/2012
|
Letter stating that this is a second request to extend the due date until May 1st filed by D. Reinsel on behalf of Wheeling & Lake Erie Railway Company. |
02/23/2012
|
Service Notice |
02/23/2012
|
Entry that W&LE be granted an extension of time until March 23, 2012, to complete all of these projects. (SF) |
01/18/2012
|
Service Notice |
01/18/2012
|
Entry ordering W& LE be granted an extension of time until February 16, 2012, to complete all of these projects. (SF) |
01/17/2012
|
Request for an extension of time filed by P. Patton, PE, City Engineer for the City of Medina, Ohio. |
01/17/2012
|
Request to extend the due dates filed by D. Reinsel on behalf of Wheeling & Lake Erie Railway Company. |
01/13/2012
|
Correspondence letter stating that the City of Medina agrees with and fully supports Wheeling and Lake Erie's request for a time extension to May 1, 2012. filed by Patrick J. Patton, PE on behalf of the City of Medina. |
12/07/2011
|
Service Notice |
12/07/2011
|
Entry that W&LE be granted an extension of time until January 16, 2012, to complete all of these projects. (JML) |
12/06/2011
|
In-house memo filed by G. Martin that recommends the Attorney Examiner grant request for a 30 day extension of time. |
12/06/2011
|
Request by Wheeling & Lake Erie Railway Company for the ODRC and PUCO to extend the due dates on the railroad project completion filed by D. Reinsel. |
12/05/2011
|
Letter requesting a thirty day extension to give the City of Medina enough time to determine a schedule for completion filed by D. Reinsel on behalf of Wheeling Lake Erie Railway. |
06/09/2010
|
Service notice. |
06/09/2010
|
Entry ordering W&LE submit to the Commission and ORDC site plans and cost estimates for the projects by September 9, 2010; that following approval of site plans and cost estimates by ORDC, W&LE proceed with and complete the projects by December 9, 2011; that W&LE notify the Commission and ORDC 30 days before the projected date of completion; that the installations at the grade crossings are completed and the warning devices have been put in service, staff will file a memorandum in this docket indicating that the installations are completed and the warning devices have been put in service. |
05/14/2010
|
In the matter of the authorization of the Wheeling & Lake Erie Railway to upgrade a corridor in the City of Medina. |