DIS - Case Record for 09-1829-EL-BLN Skip to main content
      
      
CASE NUMBER: 09-1829-EL-BLN
CASE DESCRIPTION: OHIO EDISON COMPANY
DOCUMENT SIGNED ON: 4/23/2024
DATE OF SERVICE: ________________________________________
03/20/2015 Case Action Form to Close Cases effective 3/20/2015.
09/16/2011 Notification of completion of the V&M Star Steel Project on September 11, 2011 filed by S. Humphrys.
09/23/2010 Letter of notification advising that construction on this project is expected to begin September 2, 2010 filed on behalf of FirstEnergy Service Company by S. Humphrys.
01/26/2010 Staff investigation report and recommendation.
12/01/2009 Exhibit 1: Officials served copy of letter of notification.
12/01/2009 In the matter of the letter of notification of American Transmission Systems, Incorporated and Ohio Edison Company for Hunt 138 kV transmission line extension to V & M Star Steel.