08/28/2023
|
Notice of Withdrawal of Matthew W. Warnock electronically filed by Teresa Orahood on behalf of Devin D. Parram. |
01/26/2023
|
Notice of Blue Creek Decommissioning Performance Bond - Continuation of Certificate that covers 2022-2027 electronically filed by Mr. Peter F. Landoni on behalf of Avangrid Renewables. |
02/16/2022
|
Report 2022 Blue Creek Wind Farm Decommissioning Study electronically filed by Mr. Peter F. Landoni on behalf of Avangrid Renewables. |
04/02/2019
|
Case action form to reopen case. |
03/28/2019
|
Case Action Form closing case with an effective date as of 3/28/19. |
02/23/2017
|
Blue Creek Wind Farm Decommissioning report 2017. electronically filed by Mr. Peter F Landoni on behalf of Avangrid Renewables. |
02/21/2017
|
Blue Creek Decommissioning report (updated filing). electronically filed by Mr. Peter F Landoni on behalf of Avangrid Renewables and Landoni, Peter F Mr. |
02/16/2017
|
Blue Creek Wind Farm Decommissioning Report electronically filed by Mr. Peter F Landoni on behalf of Avangrid Renewables and Mr. Peter F Landoni. |
05/12/2016
|
Notice of Withdraw and Substitution of Counsel of Ohio Hospital Association electronically filed by Teresa Orahood on behalf of Matthew W. Warnock. |
05/03/2016
|
Notice of Change of Address for counsel for the Ohio Power Siting Board, effective May 9, 2016. electronically filed by Kimberly L Keeton on behalf of Ohio Power Siting Board. |
05/01/2013
|
Public comment response letter to Hoaglin Township Trustees from PUCO Chairman T. Snitchler. |
02/04/2013
|
Case Action Form Reopening Cases electronically filed by Mr. Jeffrey R Jones on behalf of Public Utilities Commission of Ohio. |
02/04/2013
|
Memo closing case with an effective date of 2/4/13 electronically filed by Mr. Jeffrey R. Jones on behalf of Public Utilities Commission of Ohio. |
10/01/2012
|
Correspondence of Van Wert County Engineer stating opinion on the final condition of the roadways used by Iberdrola and their contractors during the construction of the Blue Creek Wind Farm, filed by K. J. Wendel, PE, PS - Van Wert County Engineer. |
10/01/2012
|
Case status form reopening case. |
09/25/2012
|
Case Action Form to Close cases effective 09/25/2012 filed by J. Jones. |
08/31/2012
|
Spreadsheet documenting a sound spot check conducted on March 19, 2012. The Facility was in compliance with their Certificate electronically filed by Mr. Nicholas E. Doss on behalf of The Ohio Power Siting Board. |
08/31/2012
|
Additional information on Blue Creek Wind Farm filed by PUCO Staff. |
06/27/2012
|
Letter stating that the Ohio Power Siting Board requires Iberdrola to repair Hoaglin Township roads to preconstruction condition as required by stipulation 41 and ORC filed by Hoaglin Township Trustees.
|
06/26/2012
|
Notice that the Blue Creek Wind Farm achieved Commercial Operation on June 14, 2012 filed by P. Landoni. |
04/19/2012
|
OPSB Response letter sent to Kyle J. Wendel filed by Chairman Snitchler. |
03/30/2012
|
Response letter to Mr. J. Roppe regarding the Blue Creek Wind Farm Project from K. Wissman, OPSB. |
03/21/2012
|
Response including executed surety bond to meet the decommissioning requirements filed by Catherine Reinhart on behalf of Iberdorola Renewables. |
07/21/2011
|
OPSB public response letter sent to Gene Pool regarding potential noise levels caused by wind turbines filed by R. Straum on behalf of K. Wissman. |
07/14/2011
|
OPSB public response letter sent to: Milo Schaffner filed by K. Wissman on behalf of OPSB. |
06/02/2011
|
Correspondence to Submit Updated Complaint Resolution Procedure electronically filed by Teresa Orahood on behalf of Blue Creek Wind Farm, LLC. |
05/20/2011
|
OPSB public comment response to Iberdrola Renewables, Inc. in reference to the Blue Creek Wind Farm, LLC filed by Kim Wissman on behalf of the Ohio Power Siting Board. |
05/10/2011
|
Response to the Blue Creek Wind Farm inquiries of Hoaglin and Tully Township Board of Trustees from Director Kim Wissman on the behalf of Ohio Power Siting Board. |
04/29/2011
|
The Boards of Trustees of Hoaglin Township and Tully Township in Van Wert County respectfully request a determination from the Ohio Power Siting Board, in response to our earlier communication of March 7, 2011 filed by W. Kemler and P. Kreischer. |
04/05/2011
|
Response of Blue Creek Wind, LLC to the March 22, 2011 letter from Hoaglin and Tully Townships filed by S. Bloomfield. |
03/22/2011
|
Hoaglin Township Trustees meeting minutes filed by A. Ostring, W. Kemler, and M. Schaffner. |
03/22/2011
|
Tully Township meeting minutes filed by P. Kreischer, Chairman and K. Baxter, Fiscal Officer. |
03/22/2011
|
Request of the Ohio Power Siting Board regarding township transportation permits filed by the Board of Trustees of Hoaglin Township and Tully Township in Van Wert County. |
03/22/2011
|
Notice of Record of Proceedings filed by the Hoaglin Township Trustees on behalf of the Hoaglin Township Trustees. |
03/08/2011
|
Letter regarding authorization of the commencement of construction on the balance of the Wind Farm project filed by K. Lambeck, OPSB. |
12/06/2010
|
Response letter sent to Gene D. Pool filed by the Staff of OPSB. |
12/06/2010
|
Letter with concern in regard to wind turbines and to give consideration to make an adjustment in moving the two or three turbines east and west of their house 150 ft. south of their current site, and to shut down blade rotation at the 30 hour shadow flicker exposure limit filed by J. P. Hotmire. |
12/03/2010
|
Notice regarding the start of construction electronically filed by Teresa Orahood on behalf of Heartland Wind Energy LLC. |
11/23/2010
|
Correspondence submitting Responses to Staff Data Requests - Part 11 electronically filed by Teresa Orahood on behalf of Heartland Wind Energy LLC. |
11/23/2010
|
Correspondence submitting Responses to Staff Data Requests - Part 10 electronically filed by Teresa Orahood on behalf of Heartland Wind Energy LLC. |
11/23/2010
|
Correspondence submitting Responses to Staff Data Requests - Part 9 electronically filed by Teresa Orahood on behalf of Heartland Wind Energy LLC. |
11/23/2010
|
Correspondence submitting Responses to Staff Data Requests - Part 8 electronically filed by Teresa Orahood on behalf of Heartland Wind Energy LLC. |
11/23/2010
|
Correspondence submitting Responses to Staff Data Requests - Part 7 electronically filed by Teresa Orahood on behalf of Heartland Wind Energy LLC. |
11/23/2010
|
Brief submitting Responses to Staff Data Requests - Part 6 electronically filed by Teresa Orahood on behalf of Heartland Wind Energy LLC. |
11/23/2010
|
Correspondence submitting Responses to Staff Data Requests - Part 5 electronically filed by Teresa Orahood on behalf of Heartland Wind Energy LLC. |
11/23/2010
|
Correspondence submitting Responses to Staff Data Requests - Part 4 electronically filed by Teresa Orahood on behalf of Heartland Wind Energy LLC. |
11/23/2010
|
Correspondence submitting Responses to Staff Data Requests - Part 3 electronically filed by Teresa Orahood on behalf of Heartland Wind Energy LLC. |
11/23/2010
|
Correspondence submitting Responses to Staff Data Requests - Part 2 electronically filed by Teresa Orahood on behalf of Heartland Wind Energy LLC. |
11/23/2010
|
Correspondence submitting Responses to Staff Data Requests - Part 1 electronically filed by Teresa Orahood on behalf of Heartland Wind Energy LLC. |
11/19/2010
|
Service notice. |
11/18/2010
|
Entry ordering that the joint application to transfer the certificate from Heartland to Blue Creek be granted in accordance with finding (4). (OPSB) |
10/29/2010
|
Drilling and Blasting Company Safety Policies filed on behalf of Dynamic Rock Solutions. |
10/15/2010
|
Joint application to transfer a certificate to Blue Creek Wind Farm, LLC filed by S. Bloomfield on behalf of Heartland Wind, LLC and Blue Creek Wind Farm, LLC. |
09/27/2010
|
Tree Clearing Plan on behalf of Blue Creek Wind Farm filed by Blattner Energy, Inc. |
09/27/2010
|
Frac-Out Contingency Plan for Horizontal Directional Drill filed on behalf of and by The Blue Creek Wind Farm. |
09/24/2010
|
Decommissioning plan filed on behalf of Blue Creek Wind Farm. |
09/23/2010
|
Emergency Response Plan filed on behalf of Blattner Energy, Blue Creek. |
09/21/2010
|
Interim interconnection service agreement of PJM Interconnection, LLC, Iberdrola Renewables, Inc. and Ohio Power Company, filed by A. Elmy on behalf of PJM Interconnection, LLC, S. Jacobson on behalf of Iberdrola Renewables, Inc., M. Heyeck on behalf of Ohio Power Company. |
09/21/2010
|
Response letter sent to Ms. Sally W. Bloomfield on behalf of Ohio Power Siting Board, filed by K. Lambeck. |
08/24/2010
|
Response letter to Brian K. Brakebill from K. Wissman, OPSB. |
08/24/2010
|
Response letter to David R. Winters filed by K. Wissman, OPSB. |
08/24/2010
|
Service Notice |
08/23/2010
|
Service Notice |
08/23/2010
|
Opinion and order stating that the stipulation be approved and adopted, a certificate be issued to Heartland pursuant to Chapter 4906, Revised Code, for the construction, operation, and maintenance of the wind powered electric generating facility, subject to conditions set forth in the stipulation. (OPSB) |
08/19/2010
|
Letter in support of The Blue Creek Wind Farm filed by J and C Thomas. |
08/18/2010
|
Letter supporting Heartland Wind's (Iberdrola) current application, filed by Brian Brakebill. |
08/17/2010
|
Letter regarding proposed construction of Blue Creek Wind Farm on behalf of Livingston County Highway Department filed by D Winters. |
08/12/2010
|
Letter on behalf of Iberdrola Renewables filed by D. Litchfield in response to OPSB filing by Mr. Schaffiner, dated August 6, 2010. |
08/12/2010
|
Response letter mailed to J. Harmon, Van Wert County Township Association from K. Wissman, OPSB. |
08/11/2010
|
Letter of Hoaglin, Union and Tully Townships in Van Wert County Ohio are respectfully asking OPSB to allow each Township to become an Intervenor in this case filed by Milo Schaffner on behalf of Hoaglin, Union and Tully Townships Trustees . |
08/06/2010
|
Letter regarding drawings mailed to OPSB in compliance with Condition No. 56(a) of the Joint Stipulation and Recommendation filed on July 14, 2010, filed by S. Bloomfield on behalf of Heartland Wind Energy, LLC. |
08/02/2010
|
Transcript of Heartland Wind, LLC hearing held on 07/15/10. electronically filed by Mrs. Jennifer Duffer on behalf of Armstrong & Okey, Inc. and Anderson, Rosemary Foster Mrs. |
07/28/2010
|
Letter serving as notice that Gamesa G90 2.0 MW wind turbine has been selected for the construction project filed by D. Litchfield on behalf of Heartland Wind Energy LLC. |
07/23/2010
|
Exhibits for hearing held July 8, 2010 before Jay Agranoff and L. Douglas Jennings. |
07/23/2010
|
Transcript for 7/8/10 hearing held in Van Wert, Ohio electronically filed by Mrs. Jennifer Duffer on behalf of Armstrong & Okey, Inc. and Jones, Maria DiPaolo Mrs. |
07/20/2010
|
Response to Brett Heffner comments filed by D. Litchfield on behalf of Blue Creek Wind Farm. |
07/20/2010
|
Response to the comments of Jason Gray filed by D. Litchfield on behalf of Blue Creek Wind Farm. |
07/16/2010
|
Correspondence regarding testimony of Dan Litchfield filed by B. Heffner. |
07/15/2010
|
Letter commenting on Mr. Litchfield's comments filed by J. Gray. |
07/14/2010
|
Response to Ohio Power Siting Board filed by D. Litchfield on behalf of Heartland Wind Energy LLC. |
07/14/2010
|
Joint stipulation and recommendation filed by J. Jones on behalf of The Ohio Power Siting Board, C. Grasseschi on behalf of The Attorney General, L. Gearhardt on behalf of the Ohio Farm Bureau Federation, and S. Bloomfield on behalf of Heartland Wind LLC. |
07/14/2010
|
Direct testimony of Dan Litchfield on behalf of Heartland Wind LLC filed by S. Bloomfield. |
07/09/2010
|
Motion for an extension of time to file additional testimony with memorandum in support, filed by S. Bloomfield on behalf of Heartland Wind LLC. |
07/09/2010
|
Direct testimony of Dan Litchfield on behalf of Heartland Wind LLC. |
07/09/2010
|
Response letter sent to E. Ludwig filed on behalf of the OPSB. |
07/08/2010
|
Proof of publication. (Paulding, Van Wert, and Allen Counties) |
07/08/2010
|
Letter to Jason Gray filed by D. Gentry-Davis on behalf of The Public Utilities Commission of Ohio. |
07/06/2010
|
Joint list of issues, filed by S. Bloomfield and L. Gearhardt, on behalf of Heartland Wind, LLC and Ohio Farm Bureau Federation. |
06/28/2010
|
Response from Stoneco Inc/The Shelly Company with respect to the non-operation of the quarry during November through March filed by S. Bloomfield. |
06/28/2010
|
Letter providing Heartland Wind Energy LLC's response to the letter of Wayne Warren to the Ohio Power Siting Board submitted on June 22, 2010 filed by D. Litchfield. |
06/25/2010
|
Response letter sent to Dennis Stout, filed by K. Wissman on behalf of the Ohio Power Siting Board. |
06/25/2010
|
Response letter sent to Robert and Barbara Stanley, filed by K. Wissman on behalf of the Ohio Power Siting Board. |
06/25/2010
|
Response letter sent to James R. Clark filed by K. Wissman on behalf of the OPSB. |
06/25/2010
|
Response letter sent to Ronald Schmidt, filed by K. Wissman on behalf of the Ohio Power Siting Board. |
06/25/2010
|
Response letter sent to Albert and Betty Taylor filed by K. Wissman on behalf of the OPSB. |
06/25/2010
|
Response letter sent to Cheryl Griffith filed by K. Wissman on behalf of the OPSB. |
06/25/2010
|
Response letter to Jason Schaffner, filed by K. Wissman on behalf of the Ohio Power Siting Board. |
06/25/2010
|
Response letter sent to Ann Ayers filed by K. Wissman on behalf of the OPSB. |
06/25/2010
|
Response letter sent to Greg Grentman filed by K. Wissman on behalf of the OPSB. |
06/25/2010
|
Response letter sent to Don and Judith Baer filed by K. Wissman on behalf of the OPSB. |
06/25/2010
|
Response letter sent to Doug Beck filed by K. Wissman on behalf of the OPSB. |
06/25/2010
|
Response letter sent to Paula Stout filed by K. Wissman on behalf of the OPSB. |
06/25/2010
|
Response letter sent to Wayne and Ellyn Warren filed by K. Wissman on behalf of the OPSB. |
06/25/2010
|
Response letter sent to Lois Harris filed by K. Wissman on behalf of the OPSB. |
06/25/2010
|
Response letter sent to Joel Williams filed by K. Wissman on behalf of the OPSB. |
06/25/2010
|
Response letter sent to Bryan Dunham filed by K. Wissman on behalf of the OPSB. |
06/25/2010
|
Response letter sent to John E. Grubaugh filed by K. Wissman on behalf of the OPSB. |
06/25/2010
|
Response letter sent to Lisa Line filed by K. Wissman on behalf of the OPSB. |
06/25/2010
|
Response letter sent to Robert and Eunice D. Mefferd filed by K. Wissman on behalf of the OPSB. |
06/25/2010
|
Response letter sent to Greg and Cheryl Schaffner, filed by K. Wissman on behalf of the Ohio Power Siting Board. |
06/25/2010
|
Response letter sent to Brian Schaffner, filed by K. Wissman on behalf of the Ohio Power Siting Board. |
06/25/2010
|
Response letter sent to Beverly Jo Schaffner, filed by K. Wissman on behalf of the Ohio Power Siting Board. |
06/25/2010
|
Response letter sent to James and Jane Poling, filed by K. Wissman on behalf of Ohio Power Siting Board. |
06/25/2010
|
Response letter sent to Troy and Tina Miller, filed by K. Wissman on behalf of Ohio Power Siting Board. |
06/25/2010
|
Response to James and Maureen Grubaugh filed on behalf of Ohio Power Siting Board by K. Wissman. |
06/23/2010
|
Service Notice for Staff Report. |
06/23/2010
|
Staff Report electronically filed by Mr. James S. O'Dell on behalf of Staff of OPSB. |
06/23/2010
|
Letter and petition in opposition to the Heartland Wind, LLC case filed by W. Warren, consumer. |
06/22/2010
|
Correspondence stating wind power is not reliably produced, winds blow intermittently, and wind generators do not reliably generate in sync with demand curves filed by concerned citizen, Wayne Warren. (FAX) |
06/16/2010
|
Proof of publications in Allen, Van Wert, and Paulding counties filed on behalf of Heartland Wind, LLC by S. Bloomfield. |
06/02/2010
|
Letter to Arthur Fiock and Milo Schaffner advising them the correct public hearing date for Heartland Wind LLC is July 8, 2010; at 5:00 p.m., at the Lincolnview School, 15945 Middle Point Road, Van Wert, Ohio 45891. Filed by OPSB Staff.
|
05/28/2010
|
Letter informing the public that on July 7, 2010, a public hearing for Heartland Wind LLC is scheduled at 5:00 p.m. at the Lincolnview School, 15945 Middle Point Road, Van Wert, Ohio 45891 filed by Staff. |
05/26/2010
|
Letter asking that Intersection #26 not be approved as drawn and proposed filed by M. Schaffner, Tenant Farmer and A. Fiock, Owner |
05/17/2010
|
Correspondence concerning data requests pertinent to the Staff Investigation in this matter, Heartland Wind, LLC has determined that the Mitsubishi turbines would no longer be considered along with two other models for this project filed by S. Bloomfield. |
05/06/2010
|
Service Notice. |
05/06/2010
|
Entry ordering that the joint motion to reschedule the hearings and establish a new procedural schedule be granted in accordance with finding (6); public and evidentiary hearings be rescheduled consistent with finding (6); Heartland shall post notice and cause newspaper notice to be published concerning the rescheduling of hearings. (JSA) |
04/30/2010
|
Joint motion for an extension of time or continuance of hearing dates and memorandum in support filed by M. Warnock on behalf of Heartland Wind, LLC and J. Jones on behalf of the Public Utilities Commission of Ohio. |
04/01/2010
|
Service Notice |
04/01/2010
|
Entry ordering that the joint motion to reschedule hearings and establish a new procedural schedule be granted; public and evidentiary hearings be rescheduled consistent with finding (5); the parties comply with the revised procedural schedule; Heartland shall post notice and cause newspaper notice to be published concerning the rescheduling of hearings. (JA) |
03/31/2010
|
Application supplement ( Part 3 of 3 ). |
03/31/2010
|
Application Supplement ( Part 2 of 3 ). |
03/31/2010
|
Application supplement of Heartland Wind, LLC. filed by S. Bloomfield. ( Part 1 of 3 ) |
03/31/2010
|
Proof of service of application supplement filed by S. Bloomfield on behalf of Heartland Wind Energy LLC. |
03/25/2010
|
Joint motion for an extension of time or continuance of hearing dates pursuant to Ohio Administrative code Rule 4906-7-13 and memorandum in support filed by M. Warnock on behalf of Heartland Wind, LLC and J. Jones on behalf of Staff, PUCO. |
03/02/2010
|
Service notice. |
03/02/2010
|
Entry ordering a local public hearing on this matter be held on May 18, 2010, at 5:00 p.m. at the Crestview School, 531 East Tully Street, Convoy, Ohio 45832; that the adjudicatory hearing will be on June 2, 2010, at 10:00 a.m., 11th floor, hearing room D, at the offices of the Puclic Utilities Commission, 180 East Broad Street, Columbus, Ohio 43215; that OFBF's motion to intervene is granted. (JA) |
02/19/2010
|
Correspondence letter stating that the Ohio Power Siting Board has received sufficient information to begin its review of the application for certification, filed by Staff on behalf of the Staff of the Ohio Power Siting Board and the Public Utilities Commission of Ohio. |
02/19/2010
|
Proof of service of application on local public officials and libraries filed by S. Bloomfield on behalf of Heartland Wind Energy LLC. |
01/07/2010
|
Motion to intervene and memorandum in support. Filed by L. Gearhardt on behalf of Ohio Farm Bureau Federation. |
12/21/2009
|
Application continued. (Part14) |
12/21/2009
|
Application continued. (Part 13) |
12/21/2009
|
Application continued. (Part 12) |
12/21/2009
|
Application continued. (Part 11) |
12/21/2009
|
Application continued. (Part 10) |
12/21/2009
|
Application continued, (Part 9) |
12/21/2009
|
Application continued. (Part 8) |
12/21/2009
|
Application continued. (Part 7) |
12/21/2009
|
Application continued. (Part 6) |
12/21/2009
|
Application continued. (Part 5) |
12/21/2009
|
Application, Volume 2, continued. |
12/21/2009
|
Application continued. (Part 4) |
12/21/2009
|
Application continued. (Part 3) |
12/21/2009
|
Application continued. (Part 2) |
12/21/2009
|
Application of Heartland Wind, LLC for a certificate to site a wind-powered electric generation facility in the counties of Van Wert and Paulding, Ohio. (Part 1) |
12/11/2009
|
Service Notice. |
12/11/2009
|
Entry ordering that the motion for waivers, as amended, filed by the applicant be granted. (JRJ) |
11/27/2009
|
Memo addressing a motion for waivers filed by applicant, Heartland Wind, LLC, on November 6, 2009, and a subsequent clarification motion filed on November 24, 2009, Staff does not object to waiver requests filed on behalf of the OPSB by K. Lambeck. |
11/24/2009
|
Clarification to motion to waivers filed on behalf of Heartland Wind, LLC by S. Bloomfield. |
11/16/2009
|
Proof of publication in Allen, Paulding and Van Wert Counties filed on behalf of Heartland Wind, LLC by S. Bloomfield. |
11/06/2009
|
Motion for waivers and memorandum in support filed by S. Bloomfield on behalf of Heartland Wind, LLC. |
11/06/2009
|
In the matter of the notice to file application of Heartland Wind, LLC for a certificate to site a wind-powered electric generation facility in Van Wert County, Ohio and Paulding County, Ohio. |